Skip to main content
🇲🇾 11 years in Malaysian property · Every figure sourced and dated
Buying Guide · Stage 5: After you get the keys

Defect Liability Period (DLP) in Malaysia: Defect Inspection Checklist & How to Claim from the Developer

The defect liability period in Malaysia is 24 months from vacant possession, and the developer must fix any defect within 30 days of your written notice; if it doesn’t, you can repair it yourself and recover the cost, including from the sum the developer’s lawyer holds as stakeholder. Below: a room-by-room inspection checklist, the letter sequence that works, and what to do after the DLP ends.

24-month DLP30-day repair deadline5% stakeholder retentionRM10 tribunal filingVerified 2026-09-20

Short answer

The defect liability period in Malaysia is 24 months from vacant possession for homes sold under the HDA statutory SPAs, and the developer must repair within 30 days of your written notice (Schedule G clause 27, Schedule H clause 30). If it does not, you give notice of the repair cost and another 30 days, then repair and recover it, including from the stakeholder sums the developer’s solicitor holds.

Key numbers at a glance

Length of the DLP24 months from vacant possession (VP)
Contract clausesSchedule G cl.27 / Schedule H cl.30 (HDA 1966)
Developer's repair deadlineWithin 30 days of your written notice
Stakeholder sums2.5% at 8 months after VP + 2.5% at 24 months, 5% in all
On a RM600,000 unitRM15,000 + RM15,000 = RM30,000 held back
Not coveredSubsale homes; non-HDA products such as some SOHO/SOFO
Tribunal for Homebuyer ClaimsUp to RM50,000, RM10 fee, within 12 months of the DLP
After the DLPContract claims generally 6 years (Limitation Act 1953)

Key points in 30 seconds

  • For new homes sold under the HDA statutory contracts (Schedules G, H, I, J), the DLP runs 24 months from vacant possession.
  • The developer must repair within 30 days of receiving your written notice; the statutory contract cannot be varied to shorten this.
  • If it doesn’t, you give notice of your repair costs and another 30 days, then repair and recover the cost, including from the stakeholder sums (5% in total under the current schedule).
  • On a RM600,000 condo, the two 2.5% stakeholder sums add up to RM30,000, and that is your practical leverage.
  • After the DLP you can still sue in contract (generally a 6-year limitation period), and the Tribunal for Homebuyer Claims takes claims up to RM50,000 filed within 12 months of the DLP ending.

What is the defect liability period in Malaysia?

The defect liability period (DLP) is a statutory term in the sale and purchase agreement prescribed under the Housing Development (Control and Licensing) Act 1966 (HDA, Act 118). If you buy a residential unit from a licensed developer, the SPA must follow the statutory form: Schedule G (landed, sell-then-build), Schedule H (strata, sell-then-build), or Schedules I and J for build-then-sell. For a clause-by-clause walk-through, see new property SPA Schedules G, H, I and J.

DLP rules at a glance (as at September 2026)
ItemRuleWhere it comes from
Length24 months after vacant possession (VP)Schedule G clause 27 / Schedule H clause 30
Repair deadlineWithin 30 days of receiving the buyer’s written noticeSame clauses
If the developer failsBuyer may repair, recover the cost from the developer, and deduct it from sums held by the developer’s solicitor as stakeholderSame clauses
Stakeholder sumsUnder the current schedule: 2.5% released 8 months after VP + 2.5% released 24 months after VPThird Schedule of G/H
ScopeYour unit; common-property defects in strata schemes are pursued by the JMB/MCSchedule H

The clock starts at vacant possession, not when you move in or finish renovating. If you sit on the VP notice, the DLP keeps running, so book your key collection early. What must be in place before VP (CCC, water and electricity) is covered in CCC and vacant possession.

Louis’s note: subsale purchases don’t come with this statutory DLP, so the inspection has to happen before you sign (see subsale due diligence). Products on commercial titles that fall outside the HDA, such as some SOHO/SOFO units, carry whatever warranty the contract says, so have your lawyer check it before signing.

How to prepare for a new house defect inspection

At key collection you normally receive keys, access cards and a defect form (sometimes called a joint inspection form). I tell clients to inspect twice: a quick walk-through on key day, then a thorough inspection with tools within the next week or two, followed by one consolidated defect list.

  • Documents: the SPA, the VP notice, the floor plan and the developer’s specification / schedule of finishes
  • Tools: measuring tape, spirit level, a tile-tapping rod (a coin works), a socket tester, torch, masking tape, and your phone for photos and video
  • A bucket of water or a hose to test floor traps and the fall of bathroom and balcony floors
  • Confirm water and electricity are connected (a VP condition under Schedules G and H) so you can test pressure, sockets and water-heater points
  • Mark each defect with numbered tape and match the photo numbers to your list
  • Ask how the developer accepts defect reports (portal, email or counter) and how it acknowledges receipt

For large units, or if you lack the time, a professional inspector is worth considering. iProperty quotes market fees of roughly RM500 to RM3,000 depending on size and report depth (market pricing, not a regulated fee). A clear report with photos makes it harder for the developer to wave defects away as “normal”.

Missing month 8 and month 24

The developer’s solicitor releases 2.5% at 8 months after VP and another 2.5% at 24 months, which is RM30,000 on a RM600,000 unit. If your written notice of unresolved defects does not reach the solicitors before those dates, the money goes to the developer and you are left with the tribunal (capped at RM50,000) or a civil suit.

Ask Louis directly
Send me your defect list and photos and I'll tell you which items fall inside the DLP, how the notice letter should read, and who it has to go to.

I'll send you a free room-by-room inspection checklist and work out the two stakeholder sums and their due dates from your purchase price, ready to put in your calendar.

Defect inspection checklist, room by room

Floors, walls and ceilings

  • Tap every tile for hollow sounds; look for cracks, chipped edges, lippage and uneven grout
  • Walls: cracks, patchy paint, damp stains, mould; check corners with a spirit level
  • Ceilings: water marks, cracks or sagging, especially under bathrooms and air-conditioner points
  • Gaps between skirting, window sills, door frames and walls

Doors, windows and grilles

  • Every door opens, closes and locks smoothly; hinges, stoppers and locksets are complete
  • Windows and sliding doors lock tight and seals are intact; spray-test or check after rain for seepage
  • Glass scratches or cracks; dents in aluminium frames

Bathrooms, kitchen and plumbing

  • Run every tap and shower at full pressure and look for leaks
  • Floor traps drain quickly and the floor falls toward them with no ponding
  • WC flushes properly and is firmly fixed; no drips under basins and the kitchen sink
  • Water-heater and hood points match the plans

Electrical

  • Test each socket with a socket tester (earth, reversed live/neutral)
  • All switches work, the DB box is labelled, and the RCCB/ELCB test button trips
  • Air-conditioner, TV and data points match the specification in number and location

Extra checks for landed homes

  • Roof leaks (recheck ceilings after rain) and clear gutters
  • Settlement in the yard or porch, cracks in boundary walls
  • Porch gradient and the location of sewer/inspection chamber covers
Louis’s note: the most common way buyers lose DLP claims is renovating too early. Once tiles are hacked or walls altered, the developer argues the renovation caused the defect. Submit your list, let the first round of repairs finish, photograph the result, then start work. Rules for renovating are in renovation permits and management rules.

How to claim defects from the developer (and what if it ignores you)

The DLP clause works on written notice plus deadlines. Verbal complaints and WhatsApp groups are weak evidence, so keep a paper trail that proves receipt. The sequence below follows Schedule G clause 27 / Schedule H clause 30 as explained by law firms Kuek Ong and YHA:

  1. Letter 1: notice of defectsSend a numbered defect list with photos by registered post, by email with acknowledgement, or by hand against a stamped receipt. Note the date received.
  2. Wait 30 daysThe developer must repair within 30 days of receiving the notice. Check each item afterwards and photograph it; don’t sign a “all completed” sheet if items remain.
  3. Letter 2: notice of repair costsIf nothing happens, get a quotation from an independent contractor, tell the developer in writing that you intend to repair and at what cost, and give it another 30 days.
  4. Repair and keep recordsIf the deadline passes, carry out the repair and keep the quotation, invoice, receipt and before-and-after photos.
  5. Claim from the developer and the stakeholderDemand the cost from the developer and notify the developer’s solicitors in writing that a defect claim is outstanding. If your notice lands within the 8-month or 24-month window, the solicitors generally cannot release the retention until the architect certifies the defects are made good.
  6. Still unpaid: tribunal or courtFile with the Tribunal for Homebuyer Claims (up to RM50,000, RM10 fee) or take legal action.
DLP timeline: the dates that matter
WhenWhat to do
VP notice dateBook key collection promptly; the DLP runs from VP
1-2 weeks after keysFull inspection with tools; send the first written defect list
30 days after noticeDeveloper’s repair deadline; re-check and photograph each item
Before month 8 after VPNotify the developer’s solicitors of unresolved defects (first 2.5% retention falls due)
Around month 20Second full inspection after the rainy seasons
Before month 24 after VPLast defect notices must be received (second 2.5% retention falls due)
Within 12 months after the DLPFile at the Tribunal for Homebuyer Claims if still unresolved

Worked example: how much is held back?

Say you bought a RM600,000 strata unit under Schedule H. Under the current payment schedule the developer’s solicitor holds two sums after VP:
RM600,000 × 2.5% = RM15,000 (released 8 months after VP)
RM600,000 × 2.5% = RM15,000 (released 24 months after VP)
Total RM30,000. That is your leverage, so get unresolved defect notices to the solicitors before month 8 and month 24. The full schedule is in progressive payment schedule.

Check your own SPA: portals print different versions of the payment schedule (older ones show 12.5% at VP and a different retention). The figures above follow the post-2015 Schedules G and H; your SPA’s Third Schedule is what counts.

Common defects in new Malaysian homes (and what isn't one)

Common defects and what to ask for
DefectWhere it shows upWhat to ask the developer for
Hollow tilesLarge living-room and corridor floorsList quantity and location; ask for relaying and matching tile batches
Wall cracksCorners of openings, beam/brickwall jointsSeparate hairline surface cracks from structural ones; ask for a written explanation for the latter
Water seepageWindow frames, bathroom walls, ceilingsTrace and fix the source, not just repaint
Poor drainage / pondingBathrooms, balconies, kitchenRe-screed the fall or clear the pipe
Ill-fitting doors and windowsAluminium windows, sliding doorsAdjust or replace seals and ironmongery
Electrical faultsSockets, DB boxInspection and repair by a licensed electrician

Slight paint variation and fine shrinkage cracks are often called “within tolerance”. When you disagree, photos, measurements and an inspector’s report carry the argument. Leaks from the unit above, corridors and façades are common-property or inter-floor issues with a different procedure: see common property defects and water leakage.

Can you claim after the defect liability period ends?

Yes, though it gets harder. As VCC Law summarises the case law, the DLP clause is an extra remedy and does not remove your right to sue in contract, which generally carries a 6-year limitation period under the Limitation Act 1953. Latent defects, the ones you could not have spotted at handover, can also be pursued in a civil claim, but you will need an expert report and a lawyer.

Three routes compared
RouteBest forKey points
DLP clause + stakeholder sumsDefects found within 24 monthsFastest and cheapest; written notice and deadlines matter most
Tribunal for Homebuyer ClaimsClaims up to RM50,000RM10 fee, no lawyer needed; file within 12 months of the CCC, the end of the DLP or termination
Civil courtLarger or latent-defect claimsGenerally 6 years in contract; needs lawyers and experts

The tribunal process is covered in Tribunal for Homebuyer Claims. Building-wide problems such as façade leaks or lifts should be driven by the JMB or MC; see JMB, MC and COB explained.

Louis’s note: put the DLP expiry date in your calendar and do a second full inspection around month 20. Seepage and tile popping often appear only after a monsoon or two; they are still covered, but your notice must reach the developer within the 24 months.
Related questions

Related questions

Does a leak from the unit above count as my defect?

The DLP clause covers defects inside your own parcel. Water coming from the unit above is inter-floor leakage, and façades, corridors and lifts are common property, which the JMB or MC pursues with the developer under a different procedure and different deadlines. A water stain on your own ceiling still needs written notice to the developer inside the 24 months. See common property defects and leakage.

The developer wants me to sign an “all completed” form first. Should I?

No. Signing it confirms every item was made good, which makes anything left undone far harder to chase. Re-check each item, photograph it, sign only against the ones actually fixed, mark the rest “not completed” with the date, and follow up with a letter listing the items still running their 30 days. Keep the registered post slip, email acknowledgement or stamped receipt every time.

What if the developer says hollow tiles are within tolerance?

Hollow tiles are one of the most common defects. Number each affected tile, mark its location, count them, ask for relaying, and check that replacement tiles come from a matching colour batch. Slight paint variation and fine shrinkage cracks are often called acceptable; when you disagree, photos, measurements and an inspector’s report carry the argument. iProperty quotes inspection fees of about RM500 to RM3,000.

Do subsale homes come with a defect liability period?

No. The 24-month DLP is a term of the HDA statutory contract and applies only to new homes bought from a licensed developer. Subsale properties are sold as is, so the inspection has to happen before you sign, and condition and arrears must be written into the offer and the SPA. What to check is set out in subsale due diligence.

FAQ

Frequently asked questions

How long is the defect liability period in Malaysia?

For residential units sold under the HDA statutory SPAs, the DLP is 24 months from vacant possession (Schedule G clause 27, Schedule H clause 30). The developer must repair defects within 30 days of receiving written notice. Subsale purchases and non-HDA commercial products are not covered by this statutory clause.

What can I do if the developer doesn't repair defects within 30 days?

Get a contractor’s quotation, give the developer written notice of the intended repair and cost, and allow another 30 days. After that you may repair it yourself, recover the cost from the developer, and ask the developer’s solicitors to pay it from the stakeholder sums. If that fails, file at the Tribunal for Homebuyer Claims (up to RM50,000).

Do I need a professional home inspector for a new house?

No, it is optional. With a spirit level, tile-tapping rod, socket tester and a bucket of water you can find most defects yourself. For large units, or if you are short of time, a professional report is more persuasive. iProperty quotes market fees of about RM500 to RM3,000 depending on size and scope.

Can I renovate during the defect liability period?

Nothing in the law stops you, but it invites disputes: the developer may refuse to fix anything the renovation touched. Submit your defect list, let the first repairs finish and photograph them before starting. You also need management approval for strata units, or a council permit for many landed works.

Does the DLP start from key collection or from the VP notice?

The DLP runs from vacant possession. Delaying key collection after the developer’s VP notice generally won’t push the start date back; check the wording of your SPA. The simplest protection is to collect your keys soon after the notice, inspect within a week or two, and send your first written defect list early.

Can I still claim for defects after the DLP expires?

Yes. Courts have held that the DLP clause does not take away your contractual right to sue, which generally has a 6-year limitation period, and latent defects can be pursued in a civil claim. Tribunal claims must be filed within 12 months of the DLP ending and are capped at RM50,000.

Stage 5

More in this stage

Should You Refinance a Home Loan in Malaysia? Costs, Break-Even and What to Do After Full SettlementShould you refinance a home loan in Malaysia? A 0.5% cut on RM350k saves about RM97 a month but needs ~71 months to recover full costs. Plus Form 16N steps.After Buying a House in Malaysia: Utilities, Assessment Tax, Quit Rent, Insurance & Management ChecklistAfter buying a house in Malaysia: TNB deposit of about 2 months' bills, water account transfer, 3-month council notice, 31 May quit rent deadline. JB and KL.Renovation Permit Malaysia: Council Permits, Condo Management Rules & Contractor TipsRenovation permit Malaysia: when landed homes need council approval, why condos need written management approval, MBJB fee example and how to check CIDB.Renting Out Property in Malaysia: 2026 Tenancy Stamp Duty, Rental Income Tax and the Letting ProcessRenting out property in Malaysia in 2026: tenancy stamp duty now RM1–RM7 per RM250 with no RM2,400 exemption, 30-day stamping, and rental income tax examples.Selling Property in Malaysia: RPGT Rates 2026, Seller Costs and Step-by-Step ProcessSelling property in Malaysia in 2026: RPGT is 0% for citizens after year 5, buyers retain 3% or 7%, file within 60 days. Full RM600k example and seller costs.Wills and Property Inheritance in Malaysia: Joint Ownership and What Happens Without a WillProperty inheritance in Malaysia: with no will, the Distribution Act gives spouse 1/4, children 1/2, parents 1/4. Wills, probate and joint owners explained.

Louis Koh

11 years in Malaysian property · Johor Bahru & Kuala Lumpur · English & 中文

I help local buyers and cross-border buyers from Singapore with new and subsale property. Every figure in these guides is sourced; when a rule changes, I update the page and date it.

💬 Contact Louis

Stuck on this step? Ask me directly

Send me your situation — new or subsale, budget, state, and where you are in the process — and I will tell you what to do next and what to watch for.

I'll send you a free room-by-room inspection checklist and work out the two stakeholder sums and their due dates from your purchase price, ready to put in your calendar.

Louis Koh · 11 years in Malaysian property · +60 10-906 6685 · replies 9am–10pm MYT

Defect Liability Period (DLP) in Malaysia: Defect Inspection Checklist & How to Claim from the DeveloperBuying Guide · After you get the keys
WhatsApp📞 6010 9066 685