The RTS Link: Opening Date, Fare and What Is Actually Confirmed
The RTS Link opening date and fare: as at 1 October 2026 neither has been announced, by either government. Civil works are finished and the system is in testing, but the start-of-service date itself is still not a published fact – Malaysia’s ministers point to January 2027, Singapore’s Land Transport Authority project page still says end of 2026, and both sides say the date and the fare will be announced jointly. This page separates what is confirmed from what is not, with the person, the agency and the date against every line. Where nothing has been published, you get no number here – the absence is the content.
Short answer
As at 1 October 2026 the RTS Link has no announced opening date and no announced fare. Confirmed: Woodlands North and Bukit Chagar stations, 4 km, a journey of about five minutes, capacity up to 10,000 passengers per hour per direction, co-located clearance at the departure station, operator RTS Operations Pte Ltd, civil works complete and testing running to December 2026. Not announced: the fare, the currency, operating hours, frequency, ticketing, and the start date itself – Malaysia says January 2027 while Singapore’s LTA page still says end of 2026.
Key numbers at a glance
| Stations | Woodlands North (Singapore) to Bukit Chagar (Johor Bahru) |
|---|---|
| Length and journey | 4 km; about five minutes (6-8 minutes on the test ride) |
| Capacity | Up to 10,000 passengers per hour per direction at peak (LTA) |
| Clearance | Co-located CIQ: both countries at departure (not passport-free) |
| Operator | RTS Operations Pte Ltd (Prasarana and SMRT joint venture) |
| Build status | Civil works complete; testing to December 2026 (Loke, 18 Aug 2026) |
| Fare | Not announced (Jeffrey Siow, Parliament, 7 Apr 2026 – no range given) |
| Opening date | Not jointly announced: Malaysia Jan 2027 vs LTA 'end of 2026' |
Key points in 30 seconds
- Confirmed: two stations (Woodlands North to Bukit Chagar), 4 km, a journey of about five minutes, capacity up to 10,000 passengers per hour per direction at peak, co-located clearance where you clear both countries at your departure station, operator RTS Operations Pte Ltd, civil works complete, and testing running to December 2026.
- Not announced: the fare (Singapore’s Acting Transport Minister Jeffrey Siow declined to give even a range in Parliament on 7 April 2026), the currency, operating hours, frequency, ticketing – and the start-of-service date itself.
- Two different official formulations of the opening are in play: Malaysia’s ministers say January 2027, while Singapore’s LTA project page still states end of 2026. Both governments say the date and fare come jointly; Transport Minister Anthony Loke’s words on 18 August 2026 were ‘We cannot make any unilateral announcements.’
- Three things buyers get wrong: ‘passport-free’ is flatly wrong (co-located clearance means you clear both countries’ authorities before boarding); the five minutes is the train ride, not the commute (6 to 8 minutes was observed on the August 2026 test ride, before immigration, walking and waiting); and the Shuttle Tebrau’s default is to stop six months after the RTS begins – continuation is being sought, not agreed.
- The RTS changes no buying rule: foreign ownership limits, state consent under section 433B, the 3% consent levy (minimum RM30,000), the flat 8% non-citizen stamp duty and Johor’s RM1,000,000 minimum price all stand. And no government on either side has published any statement about the line’s effect on property prices.
Confirmed and not announced: the table
This table is the article. The left-hand column is what a government agency or the operator has formally stated; the right-hand side is what still has not been announced. Both halves matter, and the second one more than most people expect: if you are paying a price today that assumes what the line will do, you should first know how much of it remains unpublished.
| Item | Status | Official source and date |
|---|---|---|
| Two stations: Woodlands North (Singapore, interchange with the Thomson-East Coast Line) to Bukit Chagar (Johor Bahru) | Confirmed | Singapore Land Transport Authority (LTA) project page |
| Length: 4 km | Confirmed | LTA |
| Journey time: about five minutes | Confirmed as a train ride, not a commute | LTA: ‘about five minutes between the two stations’. The media test ride of 18 August 2026 was reported at 6 to 8 minutes each way |
| Capacity: up to 10,000 passengers per hour, in each direction, at peak | Confirmed | LTA |
| Clearance: co-located CIQ – you clear both countries at your departure station | Confirmed | LTA |
| Operator: RTS Operations Pte Ltd (RTSO), a joint venture of Prasarana Malaysia Bhd and SMRT Corporation Ltd | Confirmed | LTA |
| Civil works: complete | Confirmed | Transport Minister Anthony Loke, at Bukit Chagar, 18 August 2026 |
| Testing and commissioning: under way, to complete December 2026 | Confirmed | Loke, 18 August 2026 |
| The fare | Not announced | Singapore’s Acting Minister for Transport Jeffrey Siow, in Parliament on 7 April 2026: fares are ‘determined commercially by the operator’ and ‘The operator will announce the fares in due course’. The question had asked for an expected range; the reply gave none. Loke, 18 August 2026: discussions still ongoing |
| The fare currency (ringgit, Singapore dollars or both) | Undecided | RTSO Chief Executive Dr Ahmad Marzuki Ariffin, 26 February 2025: ‘it will be announced later’ |
| Operating hours (first and last train) | Not announced | Absent from LTA’s project page, LTA’s 2024 factsheet and the ministerial briefing of 18 August 2026 |
| Service frequency or headway | Not announced | Never stated by any official source |
| Ticketing and payment (including through-ticketing with either network, commuter concessions) | Not announced | Never stated |
| Start of passenger service | Not jointly announced | Malaysia’s ministers say January 2027; LTA’s project page still says end of 2026. Loke, 18 August 2026: the date and fare ‘will be announced concurrently together between Malaysia and Singapore’ and ‘We cannot make any unilateral announcements’ |
What is confirmed: stations, distance, capacity and clearance
Route and journey time
- Two stations: Woodlands North in Singapore, which interchanges with the Thomson-East Coast Line station by underground concourse, and Bukit Chagar in Johor Bahru. LTA’s wording: ‘Woodlands North Station in Singapore to the Bukit Chagar Station in JB’.
- Length: 4 km.
- Journey time: LTA says ‘about five minutes between the two stations’. At the media test ride on 18 August 2026 the end-to-end ride was reported as six to eight minutes each way (one headline said six minutes), with the project director citing about five. That is the train ride, not your door-to-door trip – immigration, walking and waiting are not in it, and none of the three has a published figure.
- Capacity: LTA says ‘up to 10,000 commuters during peak periods, for every hour and in each direction’.
- Operator: RTS Operations Pte Ltd (RTSO), described by LTA as ‘a joint venture company formed by Malaysia’s Prasarana Malaysia Bhd and Singapore’s SMRT Corporation Ltd’.
- The 18 August 2026 briefing put projected daily ridership at launch at 40,000. That is a ridership projection, not capacity; capacity is 10,000 per hour per direction. The two are routinely conflated and should not be.
Clearance: both countries at your departure station, which is not 'passport-free'
LTA, verbatim: “co-located Customs, Immigration and Quarantine (CIQ) facilities. Passengers travelling in either direction will clear both Singapore and Malaysia authorities at the point of departure.” LTA’s 2024 factsheet says the CIQ facilities of both countries will be co-located at Woodlands North and Bukit Chagar, so passengers clear immigration at their point of departure rather than at both ends.
- Detail on the Bukit Chagar ICQ complex, from MRT Corp RTS Link project director Zulkifli Mohamed on 18 August 2026: authentication by QR code or passport; body scanners at the arrival hall, then e-gate lanes; 100 e-gate lanes; 10 security screening lanes for physical inspection; 18 baggage scanners; a dedicated lane for passengers travelling without luggage; flagged passengers diverted to separate counters so flow is not disrupted.
- ‘Clearance in seconds’ is an aim, not a service standard. The project director said at a media briefing that clearance is intended to take seconds, and the reporting itself framed it as what the link ‘aims to’ do. No published service standard and no measured clearance time exists.
The expensive mistake is not the wrong block – it is pricing in what has not been announced: no fare, no frequency, no operating hours, no jointly announced opening, a Shuttle Tebrau whose default is to stop, and an unbuilt link bridge. If a two-year delay would make you unwilling to hold the unit, you are buying an expectation, not a property. Start with supply: the overhang explained.
Ask Louis directly
Send me the location you are looking at and I'll time the commute that exists today – route, hour, realistic duration – and give you a one-pager on exactly what is confirmed and unconfirmed about the RTS.
I'll do you a free one-pager: a peak-hour commute estimate for your location using the options that exist today, plus the current confirmed and not-announced status of the RTS Link with the source and date against each line.
Construction and testing: the official timeline
Every row below is a named minister, the operator or an agency, on a stated date. That is the reliable way to read progress – who said what, and when, rather than what a headline said.
| Date | Who | What they said |
|---|---|---|
| 15 January 2026 | Transport Minister Anthony Loke | Most physical works complete; system installation and testing under way; construction on track for completion by end-2026 |
| 3 April 2026 | Loke | Project on track for a January 2027 opening; costs stable; fare proposal to be presented by Q3 2026 |
| 24 April 2026 | RTS Operations Pte Ltd (RTSO) | Multi-train high-speed trials conducted – several trains running together at higher speeds, validating key systems including regenerative braking; project to enter the Final Field Readiness (FFR) stage in September 2026 |
| 18 August 2026 | Loke, at Bukit Chagar with MRT Corp project director Zulkifli Mohamed | Verbatim: ‘From the physical aspect, the ICQ complex and RTS Link station are already completed. We are now in the testing phase, which will be what the next few months are for.‘ Testing and commissioning to complete December 2026; remaining sequence system integration testing, final testing, trial runs, commissioning; currently in final integration testing between Malaysia and Singapore; projected daily ridership at launch 40,000 |
| 18 August 2026 | Loke | Verbatim: ‘the official announcement in terms of the actual date of operation and the fare will be announced concurrently together between Malaysia and Singapore‘ and ‘We cannot make any unilateral announcements.‘ |
| Posted 4 September 2026, reported 15 September 2026 | Singapore LTA | Photographs of the completed Woodlands North station, including the pick-up and drop-off area; the station connects to the Thomson-East Coast Line station by underground concourse and houses the CIQ facilities. The same reporting recorded that the opening date has yet to be announced |
Read the table as one sentence: the hardware is finished, the systems and processes are in testing, and the joint political announcement has not happened. Those are three separate things, and finishing the first two does not produce the third.
Why the opening date is still not confirmed
This is the most important distinction on the page and the one most often lost. As at 1 October 2026, Malaysia and Singapore have not jointly announced any start-of-service date. Two different official formulations are in play at the same time:
- Malaysia: ministers have repeatedly voiced 1 January 2027, and MRT Corp’s project director indicated 1 January 2027 at the 18 August 2026 briefing. But Loke himself did not confirm it, saying the date would be announced jointly and that ‘we cannot make any unilateral announcements’.
- Singapore: LTA’s own project page still states the target for passenger service as ‘at the end of 2026’, and LTA’s 2024 factsheet says the same. Reporting on LTA’s completed-station photographs on 15 September 2026 recorded that the opening date had yet to be announced.
- So there are two official formulations – Malaysia’s January 2027 and LTA’s end of 2026 – and neither is a jointly announced date. In keeping with how this site works, both are printed here and neither is picked for you.
Fares: the complete official record, and it contains no number
As at 1 October 2026 no fare, fare range, fare structure or fare currency has been announced by anyone with the authority to set one. Below is the entire official record I could find, in date order. Note the second-to-last row in particular: that is a parliamentary question asking specifically for an expected fare range, and the reply did not give one.
| Date | Who | Exactly what was said |
|---|---|---|
| 26 February 2025 | Dr Ahmad Marzuki Ariffin, Chief Executive Officer, RTS Operations | Verbatim: ‘The currency difference will be taken into account, whether the fare is in Malaysian ringgit or Singapore dollars or both, it will be announced later.‘ No figure, and the currency question itself was undecided |
| June 2025 | Transport Minister Anthony Loke | Fare study under way; fares to be revealed closer to launch |
| 3 April 2026 | Loke | The operator is expected to present proposed rates by the third quarter of 2026 |
| 7 April 2026 | Jeffrey Siow, Acting Minister for Transport, Singapore, answering Mr Christopher de Souza in Parliament | Verbatim: ‘Fares for the Johor Bahru-Singapore Rapid Transit System Link (RTS Link) will be determined commercially by the operator, RTS Operations Pte Ltd.‘ and ‘The operator will announce the fares in due course.‘ The question asked for an expected fare range and for affordability measures; the reply gave neither |
| 18 August 2026 | Loke | Fare discussions still ongoing; fare and opening date ‘will be announced concurrently together between Malaysia and Singapore’ |
Want to see what you can actually buy?
The rules are above; these are the actual homes. Each page lists the projects I am tracking, with published price ranges and the date each figure was checked. Tell me the area on WhatsApp and I will send the current list.
Frequency, operating hours and ticketing: none of it announced
- Operating hours (first and last train): not announced. Not on LTA’s project page, not in LTA’s 2024 factsheet, and not in any ministerial statement I read, including the 18 August 2026 briefing and test ride. A reader who needs to know whether they can catch a 6 a.m. train to work cannot know that yet.
- Frequency or headway: not announced. No ‘every X minutes’ claim has an official source. And note this: capacity is not frequency. ‘Up to 10,000 per hour per direction’ is a ceiling on throughput; a headway cannot be derived from it, and should not be published as though it could.
- Ticketing and payment: not announced. Not the medium, not through-ticketing with either country’s rail network, not concessions for frequent commuters. Nothing.
- The operator publishes the timetable, and it has not. This is not information that is hard to find; it is information that does not exist yet.
The four things buyers get wrong
1. 'Passport-free' and 'no immigration' – flatly wrong
Co-located clearance means you complete both countries’ checks once, at your departure station. It is not the absence of immigration, and it is not passport-free. The QR code the project director described is a method of identification, not an exemption from clearance. Turning ‘clear once’ into ‘walk straight through without a passport’ is marketing language with no official statement behind it.
2. 'Five minutes to Singapore' – that is the train, not the commute
LTA’s five minutes is station to station; the 18 August 2026 media test ride was reported at six to eight minutes each way. A door-to-door trip adds clearance, walking, transfers and waiting, and not one of those four has a published figure – operating hours and frequency are unannounced, and the only thing said about clearance time is an aim of seconds. So ‘a five-minute commute’ is a claim that no available data supports.
3. 'The Shuttle Tebrau will keep running' – the default is the opposite
KTMB’s Shuttle Tebrau (JB Sentral to Woodlands) is the cross-border rail option that actually exists today, which makes it more consequential to a buyer than almost anything else on this page. Under the bilateral agreement it is scheduled for termination six months after RTS operations begin. On 26 October 2023 Transport Minister Anthony Loke said: “The ministry will endeavour to negotiate this matter with Singapore to maintain this service even after the RTS is operational.” Malaysia also proposed raising shuttle trips from 31 to 36 daily and coaches from four to eight per train, taking capacity to about 13,760 passengers daily against a 2023 average ridership of 8,635 a day, pending a response from Singapore’s Immigration and Checkpoints Authority. Malaysia’s Ministry of Transport has continued to say through 2026 that it is negotiating continuation. Nothing has been agreed.
4. 'You can walk from Bukit Chagar to JB Sentral' – the bridge is not built
Per the 18-19 August 2026 reporting of Loke’s briefing, an RM60 million link bridge connecting Bukit Chagar RTS station to the KTM Komuter station at JB Sentral has been approved, with a 12-month construction timeline. No start or completion date was given. On a 12-month build approved around August 2026, it is not in place for a service starting end-2026 or January 2027. In other words, the last-mile connection on the JB side is a genuine open question, and should be treated as unknown rather than as present.
What the RTS does not change, and why 'X minutes from the station' is not evidence
The RTS Link is a railway, not a property policy. It has not changed a single buying rule:
- Foreign ownership limits and what a foreigner may buy: unchanged. See how foreigners buy property in Malaysia and the Johor foreign-buyer page.
- State consent: a foreign acquisition still requires Johor state consent under section 433B of the National Land Code, applied for per transaction.
- Consent levy: residential, 3% of value, minimum RM30,000, from 1 July 2025. The railway did not change it.
- Stamp duty on a transfer to a non-citizen: a flat 8% from 1 January 2026; Malaysian permanent residents pay the citizen scale. Full cost stack in the true cost for a foreign buyer.
- Johor’s minimum purchase price for foreigners: RM1,000,000 (Bar Council Circular 444/2024). Unchanged by the line.
- MM2H: its terms have nothing to do with the railway – see MM2H and property. Singapore buyers should also read Singaporeans buying in Johor and the Singapore buyers page.
One more thing has to be said plainly. No government body, ministry, minister, LTA, MRT Corp or RTSO on either side has published any statement projecting, claiming or quantifying an effect of the RTS Link on property prices, property demand or housing supply. I searched LTA’s newsroom, Singapore’s Ministry of Transport newsroom, the Malaysian ministerial statements in the timeline above, and NAPIC, Bank Negara and Johor state statements on the RTS and prices. There is nothing. Every ‘once the line opens, this area will rise’ you have read is somebody’s forecast – usually somebody with something to sell.
Why 'X minutes from the station' is not evidence
- It is not a verified fact but an estimate, usually walking or driving time computed with no traffic, no waiting and no queue.
- The opening date, the operating hours and the frequency are all unannounced, so ‘X minutes from the station’ cannot currently be converted into any commute time at all.
- Near a station is not the same as able to commute. Commuting needs all of these at once: a train, a train at the hour you leave, clearance that moves, and a last mile that works – see the bridge above that has not been built.
- How much expectation is already in the price? That is the real question. The checkable way to answer it is transacted prices and live rental listings for the same product in the same area, not minutes on a brochure. See how to check transacted prices and what actually drives value, and for the supply side the overhang explained.
- Walk the commute that exists todayAt peak, in both directions, by the means you would actually use now – driving, bus or the Shuttle Tebrau – and time it on your phone. That number is verifiable today. The RTS one is not.
- Treat the RTS as an option, not a premiseThe opening is not jointly announced, operating hours and frequency are unannounced, and the fare is unannounced. A decision that only makes sense if all three land a certain way is resting on things nobody has published.
- Re-run the numbers without the railwayIf you would still hold the unit happily with the line two years late, you are buying a property. If you would not, you are buying an expectation.
- Assume the Shuttle Tebrau stopsThe agreement’s default is termination six months after the RTS begins, and continuation is still being negotiated. Do not treat it as a settled fallback.
- Re-check the status before you signLook at LTA’s RTS Link project page to see whether ‘end of 2026’ has changed, and check whether a joint Malaysia-Singapore announcement has been made. Those two sources are enough; third-party speculation is not.
Related questions
What is the difference between '10,000 per hour' and '40,000 a day'?
One is capacity, the other is a projection. ‘Up to 10,000 passengers per hour per direction at peak’ is LTA’s published capacity ceiling. The ‘40,000 a day’ figure is a projection of daily ridership at launch mentioned at the 18 August 2026 briefing. They are not interchangeable, and neither can be used to derive a headway – frequency has never been announced. Anyone computing ‘a train every X minutes’ from those numbers is estimating, not quoting.
How should I estimate a Johor Bahru to Singapore commute right now?
Estimate the commute that actually exists today: drive it, take the bus, or take the KTMB Shuttle Tebrau, at peak, in both directions, and time it yourself. An RTS door-to-door time cannot be calculated at all right now – operating hours, frequency and the fare are unannounced, the only statement on clearance time is an aim of seconds, and the Bukit Chagar to JB Sentral link bridge is not built. Treat the RTS as a future extra option, not as a commuting premise.
Should I pay a premium to be near an RTS station?
That is a pricing question rather than a data question, so here is only the checkable part: the opening is not jointly announced, operating hours and frequency are unannounced, the fare is unannounced, the Shuttle Tebrau’s default is to stop, and the last-mile bridge is unbuilt. No government on either side has published anything about the line’s effect on prices. To judge how much expectation is already in a price, use transacted prices and live rental listings – see how to check transacted prices.
Where will the opening date and fare be announced?
Two sources are enough. LTA’s RTS Link project page, which still says ‘end of 2026’ – a change there is itself a signal – and a joint Malaysia-Singapore announcement. On 18 August 2026 Transport Minister Anthony Loke said the date and fare would be announced concurrently by both countries and that ‘we cannot make any unilateral announcements’, so by his own standard a one-sided report does not count. This page is as at 1 October 2026; check again after that.
Frequently asked questions
When does the RTS Link open?
As at 1 October 2026, Malaysia and Singapore have not jointly announced a start-of-service date. Two official formulations coexist: Malaysia’s ministers and MRT Corp’s project director point to January 2027, while Singapore’s LTA project page still gives the target for passenger service as end of 2026. On 18 August 2026 Transport Minister Anthony Loke said the date and the fare would be announced jointly by both countries and that ‘we cannot make any unilateral announcements’. Construction-wise, civil works are complete and testing and commissioning run to December 2026. Do not tie a purchase timetable to a particular opening day.
How much will the RTS Link fare be?
It has not been announced, and this page will not give you a number. On 7 April 2026 Singapore’s Acting Minister for Transport Jeffrey Siow told Parliament that fares ‘will be determined commercially by the operator, RTS Operations Pte Ltd’ and that the operator would announce them in due course – the question had asked specifically for an expected fare range and for affordability measures, and the reply gave neither. Earlier, on 26 February 2025, RTSO’s chief executive said even the currency, ringgit or Singapore dollars or both, was undecided. Loke said on 18 August 2026 that fare discussions were ongoing. Every figure circulating is unofficial.
How often will RTS Link trains run, and what time is the first train?
Neither has been announced. Operating hours, first and last train times and service frequency are absent from LTA’s project page, LTA’s 2024 factsheet and every ministerial statement I read, including the 18 August 2026 briefing and test ride. One thing to be careful about: capacity is not frequency. ‘Up to 10,000 passengers per hour per direction’ is a throughput ceiling and a headway cannot be derived from it. The operator publishes the timetable and has not done so. If you need this line to get to work, that part cannot be planned yet.
Is the RTS Link really passport-free, with no immigration?
No, and this is the commonest misunderstanding. LTA’s arrangement is co-located CIQ: passengers clear both countries’ authorities once, at their departure station, instead of at each end. Immigration clearance still happens and passports are still part of it. On 18 August 2026 MRT Corp’s project director described authentication by QR code or passport, 100 e-gate lanes, 10 security screening lanes and 18 baggage scanners, and said clearance was intended to take seconds – but that is an aim, and no published service standard or measured clearance time exists. ‘Passport-free’ is marketing language, not an official statement.
Will the KTMB Shuttle Tebrau keep running after the RTS opens?
The default is that it stops. Under the bilateral agreement, the Shuttle Tebrau (JB Sentral to Woodlands) is scheduled for termination six months after RTS operations begin. On 26 October 2023 Transport Minister Anthony Loke said the ministry ‘will endeavour to negotiate this matter with Singapore to maintain this service even after the RTS is operational’, and Malaysia proposed raising trips from 31 to 36 daily and coaches from four to eight, lifting capacity to about 13,760 passengers daily against a 2023 average of 8,635 a day. Malaysia’s ministry has continued through 2026 to say it is negotiating. No agreement has been announced.
Can I walk from Bukit Chagar station to JB Sentral?
Probably not at opening. Per the 18-19 August 2026 reporting of the minister’s briefing, an RM60 million link bridge between Bukit Chagar and the KTM Komuter station at JB Sentral has been approved with a 12-month construction timeline, but no start or completion date was given. On a 12-month build approved around August 2026, it will not be in place for a service beginning end-2026 or in January 2027. The last-mile connection on the JB side is a genuine unknown, so treat it as unknown when you assess a commute, not as something already there.
Will the RTS Link push Johor Bahru property prices up?
No government on either side has said so. I searched LTA’s newsroom, Singapore’s Ministry of Transport newsroom, the relevant Malaysian ministerial statements, and NAPIC, Bank Negara and Johor state statements on the RTS and property – and found no official projection, claim or quantification of any kind. Everything written about ‘the RTS and your property value’ comes from property portals, valuation consultancies, developers and agencies: commentary and marketing, however confidently written and whatever official-sounding data it cites. ‘X minutes from the station’ on a brochure is not evidence either, since the opening date, operating hours and frequency are all unannounced.
Sources & verification
- LTA Singapore — JB-Singapore RTS Link project page (stations, 4 km, five minutes, 10,000 per hour per direction, co-located CIQ, operator, 'end of 2026')
- LTA Singapore — Factsheet: Updates on the JB-Singapore RTS Link (2024)
- Singapore Ministry of Transport — parliamentary reply on expected RTS Link fare range and affordability, 7 April 2026 (Jeffrey Siow)
- Malay Mail — Loke: most physical works complete, system installation and testing under way, 15 January 2026
- New Straits Times — RTS Link construction on track for completion end-2026 (Loke), 15 January 2026
- Malay Mail — RTS Link on track for January 2027 opening, costs stable (Loke), 3 April 2026
- Malay Mail — RTS Link fare proposal to be presented by Q3 (Loke), 3 April 2026
- The Sun — RTS Link successfully conducts multi-train high-speed trials (RTSO), 24 April 2026
- The Star — RTS Link fare and opening date to be announced jointly by Malaysia and Singapore (Loke), 18 August 2026
- Paul Tan — RTS Link has entered its testing phase (Loke briefing, RM60m link bridge), 19 August 2026
- Malay Mail — RTS Link aims to fast-track immigration clearance (Zulkifli Mohamed, MRT Corp), 18 August 2026
- The Rakyat Post — RTS Link media test ride, six to eight minutes each way, 19 August 2026
- The Star — Singapore LTA offers glimpse of completed RTS station (opening date yet to be announced), 15 September 2026
- Malay Mail — RTS Link fares to reflect currency exchange, announcement later (RTSO CEO Ahmad Marzuki Ariffin), 26 February 2025
- Malay Mail — RTS Link fares to be revealed closer to launch (Loke), 30 June 2025
- EdgeProp — Ministry of Transport to negotiate continuation of Shuttle Tebrau after RTS begins operations (Loke, 26 October 2023)
- The Star TV — Malaysia hopes Singapore agrees to maintain Shuttle Tebrau
- Malay Mail — Singapore-Johor RTS Link first train demonstration completed at Woodlands North, 5 February 2026
- Bar Council Conveyancing Practice Committee — Circular No. 444/2024, 23 December 2024 (state minimum purchase prices)
- KPMG Malaysia — Budget 2026: stamp duty (4% to 8% for non-citizens from 1 January 2026)
Verified: 2026-09-20. This guide is general information, not legal, tax or financial advice. Rules and rates change — confirm in writing with your lawyer, bank or the relevant authority before you sign.
More in this stage
Louis Koh
11 years in Malaysian property · Johor Bahru & Kuala Lumpur · English & 中文
I help local buyers and cross-border buyers from Singapore with new and subsale property. Every figure in these guides is sourced; when a rule changes, I update the page and date it.
Stuck on this step? Ask me directly
Send me your situation — new or subsale, budget, state, and where you are in the process — and I will tell you what to do next and what to watch for.
I'll do you a free one-pager: a peak-hour commute estimate for your location using the options that exist today, plus the current confirmed and not-announced status of the RTS Link with the source and date against each line.
Louis Koh · 11 years in Malaysian property · +60 10-906 6685 · replies 9am–10pm MYT