One 23-storey block of 148 three-bedroom apartments on Lorong Perniagaan Seri Juru 2, filed on the government register as Pangsapuri Seri Juru Indah and 43.65% built in October 2026. The permit band straddles the mainland’s floor for foreign individuals, so foreign eligibility is decided unit by unit.

148 units23 storeys3 bed · 2 bath43.65% built

⚡ Typical reply within 15 minutes, 9am–10pm MYT · No obligation

148homes in one block
10homes on a typical floor
1.7 kmto the Juru toll plaza
One City Height (Pangsapuri Seri Juru Indah) 23-storey apartment block, artist's impression, Juru, Penang
Artist’s impression of the 23-storey apartment block · from the developer’s advertisement filed with the government register
Answer block

One City Height @ Juru, Penang at a glance

Every figure below comes from the developer’s own published material or the government register. Where neither has published something, it isn’t on this page.

Development
One City HeightRegistered as Pangsapuri Seri Juru Indah · licence held by World Corporate Construction Sdn Bhd
Where it is
Juru, mainland PenangLorong Perniagaan Seri Juru 2, Seberang Perai Tengah · postcode 14100
Tenure
FreeholdPrinted as ‘Hakmilik Kekal’ on the developer’s advertisement filed with the government register, which also states no charge on the land · the register itself does not record tenure, so your solicitor’s title search is the final word
Building
1 block · 23 storeysHomes on 15 floors, Level 8 to Level 22
Units
14810 homes on each of 14 floors, 8 on Level 13
Layouts
3 bedrooms · 2 bathrooms · 950 or 1,050 sq ftType A (30 units) and Type A1 (58 units) at 950 sq ft, Type B (60 units) at 1,050 sq ft · built-up areas from the developer’s advertisement filed with the government register
Facilities
Recreational facilities, not itemisedThe filed advertisement describes a 23-storey apartment block with recreational facilities but does not list them — ask me for the facilities plan
Completion
Expected December 2027The date on the developer’s filed advertisement · register shows 43.65% built and on track · latest delivery 17 Jul 2028 under the first agreement
Government permit
30807-1/06-2028/0459(N)-(S)Valid 11 Jun 2025 to 10 Jun 2028
Foreign buyers
Decided unit by unitThe permit band straddles the mainland’s RM500,000 strata floor for foreign individuals
Why this address

Six things about One City Height worth knowing before you enquire

Four are reasons a mainland buyer would shortlist it. Two are things to settle first. Every figure here comes from the government housing register, the developer’s advertisement filed with it, or my own straight-line measurement.

🏗️

A real building, already 43.65% up

The register’s latest return puts the block at 43.65% built and ‘lancar’ (on track), fifteen months after the first sale and purchase agreement. You can stand on Lorong Perniagaan Seri Juru 2 and count the floors yourself instead of judging a scale model.

🛏️

Three bedrooms in every home

All 148 units are filed with three bedrooms and two bathrooms. There are no studios and no one-bedroom investor stock in the building, which usually means neighbours who are families and long-stay tenants, and a simpler choice for you: floor and position, not layout.

🏭

Between two industrial belts

Straight-line, the Bukit Minyak industrial area is 1.4 km away, the Juru toll plaza on the North–South Expressway 1.7 km, and the Batu Kawan Industrial Park 9.0 km. For a household working in either belt, that short commute is the whole argument for Juru.

🗂️

Most of the building is still open

When I read the register’s unit list, 27 of the 148 homes were recorded as sold and 121 as not yet sold. In practical terms you can still choose your floor and your position on the floor, which is rarely true of a block that is nearly half built.

🔎

What is still not published

The register does not record tenure or floor area for this project, and I could not find a working developer website. The developer’s advertisement filed with the register fills most of that gap: freehold tenure, built-up areas of 950 and 1,050 sq ft, three layouts and a specification list. Car parks, the list of facilities and the monthly charges are in neither source, so they stay blank on this page on purpose. I will get them in writing before you decide anything.

🏢

A first project under this licence

The register lists exactly one project under World Corporate Construction Sdn Bhd’s developer licence — this one. That is not a fault, but it means there is no delivery record on the register to judge. Read the delivery and defect clauses of the agreement carefully and follow the progress returns.

Project DNA

The whole development, decoded

Every number here is the developer’s own or the government register’s.

148Units
1Block
23Storeys
15Residential floors

Specification on the developer’s filed advertisement

Translated from the specification page of the advertisement filed with the government register. The advertisement describes the block as having recreational facilities but does not itemise them.

Structure

Whole building
  • Foundation: reinforced concrete spun piles
  • Main structure: reinforced concrete frame
  • Roof: reinforced concrete flat roof
  • Ceiling: skim coat with paint

Doors, windows and finishes

All types
  • Doors: laminated timber doors and aluminium-framed sliding glass doors
  • Windows: aluminium-framed glass windows
  • Ironmongery: approved quality locksets
  • Floors: homogeneous tiles in the living room, dining room and kitchen; ceramic tiles in the bedrooms and bathrooms
  • Walls: ceramic tiles to ceiling height in the bathrooms; plaster and paint elsewhere

Fittings in each unit

Types A and A1 · Type B
  • 1 kitchen sink with tap
  • 2 wash basins with taps
  • 2 pedestal WCs
  • 2 showers
  • 1 outdoor tap for a washing machine
  • Lighting points: 17 · 18 in Type B
  • 13-amp power points: 13 · 14 in Type B
  • 4 air-conditioner points
  • 2 electric water-heater points
  • 5 ceiling-fan points
  • 1 telephone / intercom point
  • 1 TV (Astro) point

Where the project is now

11 Jun 2025Advertising permit issued · valid to 10 Jun 2028
17 Jul 2025Date of the first sale and purchase agreement as recorded on the register
Oct 2026Register shows 43.65% built and ‘on track’ · 27 units sold, 121 not yet sold
Dec 2027Expected completion date on the developer’s advertisement filed with the government register
17 Jul 2028Latest delivery date under the first agreement — 36 months, Schedule H
Layouts

All 3 One City Height @ Juru, Penang floor plans

Three layouts, all with three bedrooms and two bathrooms. The built-up areas, the number of units of each type and the drawings come from the developer’s advertisement filed with the government register; the register itself records no floor area. The advertisement does not say which type sits where on a floor, and Level 13 has 8 homes instead of the usual 10, so ask me which type a particular unit is.

One City Height Type A floor plan, 950 sq ft, three bedrooms and two bathrooms, Juru, Penang

Type A — 950 sq ft

Built-up 950 sq ft · living and dining rooms, kitchen, drying yard, two balconies and a patio · drawn 9,000 mm × 11,900 mm overall · drawing and figures from the developer’s advertisement filed with the government register

🛏 3 Bed🛁 2 Bath30 unitsOfficial drawing
Get this floor plan
One City Height Type A1 floor plan, 950 sq ft, three bedrooms and two bathrooms, Juru, Penang

Type A1 — 950 sq ft

Built-up 950 sq ft · drawn as the mirror image of Type A, with the same room sizes · the most common type in the block · drawing and figures from the developer’s advertisement filed with the government register

🛏 3 Bed🛁 2 Bath58 unitsOfficial drawing
Get this floor plan
One City Height Type B floor plan, 1,050 sq ft, three bedrooms and two bathrooms, Juru, Penang

Type B — 1,050 sq ft

Built-up 1,050 sq ft · a larger living room and a larger main balcony than Types A and A1 · drawn 8,942 mm × 12,150 mm overall · drawing and figures from the developer’s advertisement filed with the government register

🛏 3 Bed🛁 2 Bath60 unitsOfficial drawing
Get this floor plan
Location & connectivity

Where One City Height @ Juru, Penang sits

Juru is in Seberang Perai Tengah on the Penang mainland, south of Bukit Mertajam and north of the Batu Kawan industrial corridor. The block stands on Lorong Perniagaan Seri Juru 2 — 1.7 km in a straight line from the Juru toll plaza on the North–South Expressway and 1.4 km from the Bukit Minyak industrial area. The developer’s own location map, from the filed advertisement, draws the site north of the North–South Expressway, between Jalan Juru and Jalan Bukit Tambun and near SJK(C) True Light.

Open in Google Maps →
📍 5.309167, 100.44069114100 Simpang Ampat

Pinned to the coordinates filed with the national housing register for project 30807-1. The public map listing for One City Height on Lorong Perniagaan Seri Juru 2 is about 100 m from that point. Distances are straight-line from the register’s coordinates.

What the map does not tell you. An industrial area 1.4 km away is good for the commute and for finding tenants; it also means lorries and shift-change traffic on the roads around you. Straight-line distances say nothing about that. Drive from the site to the toll plaza and to your workplace at 7.30 am and again at 6 pm before you commit, and walk the commercial lots around Lorong Perniagaan Seri Juru in the evening to see how busy they really are.
  • Pangsapuri Seri Juru (completed 26-storey block)135 mstraight-line
  • Bukit Minyak industrial area1.4 kmstraight-line
  • Juru toll plaza, North–South Expressway1.7 kmstraight-line
  • Bukit Minyak Health Clinic2.1 kmstraight-line
  • Juru Auto City3.5 kmstraight-line
  • SMJK Jit Sin, Bukit Mertajam3.9 kmstraight-line
  • AEON Mall Bukit Mertajam4.3 kmstraight-line
  • Batu Kawan Industrial Park9.0 kmstraight-line
  • Penang Bridge11.6 kmstraight-line
The government record

On the government register it is project 30807-1 — 148 units at 43.65% built

The register does not use the marketing name. The project is filed as Pangsapuri Seri Juru Indah, and the housing developer’s licence is held by World Corporate Construction Sdn Bhd (30807). I matched it to One City Height by location and building status: it is the only apartment block in this pocket of Juru that the register shows under construction.

Project codeRegistered nameAdvertising permitPermit expiresUnitsBed / bathStatus
30807-1Pangsapuri Seri Juru Indah — flats / condominium, 23 storeys30807-1/06-2028/0459(N)-(S)10 Jun 20281483 / 243.65% built · on track

Swipe sideways to see the full table →

How to run this check yourself — the seven status words, why searching by marketing name fails, and the register status of all 175 developments on this site →

Read from teduh.kpkt.gov.my on 2 October 2026. Check it yourself: teduh.kpkt.gov.my/semakan-status-kemajuan?kodProjek=30807-1

148 units on the register, and where they sit

The register files the project as one component of 148 flat / condominium units in a 23-storey building, each with three bedrooms and two bathrooms. Its unit list runs from Level 8 to Level 22: 10 homes on each of 14 floors and 8 on Level 13, which adds up to 148. On the day I read it, 27 units were recorded as sold and 121 as not yet sold.

What the permit band means against the foreign floor

The advertising permit records a minimum of RM462,000 and a maximum of RM554,000. That is the band on the advertising permit, not the price of any unit. On the mainland a foreign individual may buy strata property from RM500,000 and a foreign company from RM1,000,000, so the band straddles the individual floor: eligibility is decided unit by unit at the price in the sale and purchase agreement, with state consent and the state levy on top.

Schedule H, 36 months, no extension on record

The sale and purchase agreement is Schedule H (strata), with the standard 36-month delivery period and no approved extension recorded. The register shows the first agreement dated 17 July 2025, which puts the latest delivery date under that agreement at 17 July 2028. Your own clock runs 36 months from the date of your agreement.

43.65% built, certificate still to come

The latest return reports the block at 43.65% complete and ‘lancar’ (on track). The certificate of completion and compliance and vacant possession are not yet recorded. The advertising permit runs to 10 June 2028, a few weeks before the first agreement’s delivery date, so a renewal is something to watch for if sales continue that long.

Track record

About World Corporate Construction

The housing developer’s licence for this block is held by World Corporate Construction Sdn Bhd, developer code 30807, whose business address on the register is in Taman Bagan Jermal, Butterworth. The register lists one project under that licence, and this is it.

The name One City Height does not appear on the register. I matched it to project 30807-1 in two ways: the public map listing for One City Height on Lorong Perniagaan Seri Juru 2 sits about 100 m from the register’s coordinates, and 30807-1 is the only apartment block in this pocket that the register shows under construction. The project code printed on your sale and purchase agreement is the final confirmation — check that it reads 30807-1.

The building next door is a useful reference. Pangsapuri Seri Juru, 135 m away, is a 26-storey block that also has 148 units; it is licensed to a different company, Paramount Garden Sdn Bhd, and the register shows it completed with its certificate of completion and compliance dated 5 April 2024. It shows you what a finished tower in this exact pocket looks like, so visit both on the same trip.

One honest caveat: I could not find a working developer website for One City Height, and the web address printed on the developer’s advertisement did not lead to a developer site when I checked on 5 October 2026. That advertisement, filed with the government register, is my source for the tenure, the built-up areas, the unit mix by type, the specification, the expected completion date and the artist’s impression, location map and floor plans on this page. It does not give car parks, a facilities list or monthly charges, and I have left those blank instead of filling them in from property portals. Ask me and I will get each of them from the developer in writing.

Straight answers

Frequently asked questions

How many units are there at One City Height?

148 apartments in a single 23-storey block, according to the government register, where the project is filed as Pangsapuri Seri Juru Indah (30807-1).

The homes sit on 15 floors from Level 8 to Level 22 — 10 on each of 14 floors and 8 on Level 13.

Is One City Height freehold or leasehold?

Freehold, according to the developer’s advertisement filed with the government register: it prints the land tenure as ‘Hakmilik Kekal’ and states that there is no charge on the land. The register itself does not record tenure for this project.

Whatever any advertisement says, the title search your solicitor runs before you sign is the final word on tenure and on any charge registered against the land.

What are the unit sizes and layouts at One City Height?

Every one of the 148 units has three bedrooms and two bathrooms. The developer’s advertisement filed with the government register gives two built-up sizes: 950 sq ft for Type A (30 units) and Type A1 (58 units), and 1,050 sq ft for Type B (60 units). The register itself records no floor area.

The three floor plans on this page are the drawings from that advertisement. It does not say which type sits where on each floor, so message me the unit you are looking at and I will tell you its type.

Can foreigners buy at One City Height?

Possibly, unit by unit. The permit band runs from RM462,000 to RM554,000, and the mainland floor for a foreign individual buying strata property is RM500,000 — so a unit priced at or above the floor in the agreement can qualify and one below it cannot. A foreign company needs RM1,000,000 and is therefore out.

A foreign purchase also needs state consent, carries a 3% state levy on approval, cannot be resold for three years, and pays a flat 8% stamp duty as a non-citizen. Bumiputera-quota units are closed to foreigners. Tell me your nationality and I will check the specific unit before you pay anything.

When will One City Height be completed?

The developer’s advertisement filed with the government register gives December 2027 as the expected completion date. The register showed the block 43.65% built and on track in October 2026.

Contractually, delivery is 36 months from your sale and purchase agreement under Schedule H. The first agreement on the register is dated 17 July 2025, so the latest date under that agreement is 17 July 2028.

Which floor and which unit should I choose?

With one bedroom count across the building, the choice is about position. The unit list starts at Level 8, so ask what occupies the floors below, which homes face the industrial side and which face Bukit Mertajam, and how far each is from the lifts on a 10-home floor.

Level 13 has 8 homes instead of 10 — ask me why, because a floor with fewer homes sometimes means a facility on that level or larger corner units. With 121 units not yet sold when I read the register, you still have a real choice.

What is the price and the maintenance fee?

The only public price information is the government permit band: RM462,000 minimum and RM554,000 maximum — the band on the advertising permit, not the price of any unit. I will not repeat figures from property portals.

The monthly maintenance charge and sinking fund are not published. Message me and I will send the current price list, the units still available and the charges in writing.

How does One City Height compare with Forescape @ Metrioplace?

They are 5.0 km apart in a straight line and built for different buyers. Forescape, by Metrio Group in Simpang Ampat, is one 28-storey tower of 398 freehold dual-key serviced apartments. One City Height is a smaller building — 148 freehold homes, all three-bedroom, of 950 or 1,050 sq ft — sold under Schedule H.

If you want a dual-key layout to live in one side and let the other, look at Forescape. If you want a conventional three-bedroom family apartment in a block with fewer neighbours, this is the one to view.

Is Juru practical for daily life or for renting out?

For daily life: the Bukit Minyak Health Clinic is 2.1 km away in a straight line, Juru Auto City with its restaurants 3.5 km, SMJK Jit Sin 3.9 km and AEON Mall Bukit Mertajam 4.3 km. The Juru toll plaza is 1.7 km away for trips to the island across the Penang Bridge, 11.6 km off.

For renting: demand in this pocket comes from people working in the Bukit Minyak industrial area, 1.4 km away, and in the Batu Kawan Industrial Park, 9.0 km away. I do not quote rental figures; ask me what comparable three-bedroom apartments in the completed block next door are actually letting for.

Get the current price list and unit availability

Developer pricing moves, and the good stacks go first. Tell me your budget and whether you’re buying to live in or to let — I’ll send back the units that actually fit, not a generic brochure.

No agent fee payable by the buyer on new developer launches

Louis Koh

11 years in Malaysian property · Johor Bahru, Kuala Lumpur & Penang new launches · English & 中文

I work with cross-border buyers from Singapore and further afield, and with local investors. I’ll tell you when a project isn’t right for you — that’s usually worth more than the brochure.

💬 Message Louis

Published 2026-10-02 · Last verified 2026-10-05 against the KPKT housing register (project 30807-1), the developer’s advertisement filed with it, and my own straight-line measurements. Unit availability, pricing and completion dates are set by the developer and subject to change. This page is marketing information, not an offer or a contract.

One City Height @ Juru, Penang148 units · 3 bedrooms · Juru
WhatsApp

Ask a specific question

If you would rather not use WhatsApp, use this. I answer them myself. Only your name and one contact method are required.

Email or phone — one is enough

What you send is emailed to me and stored on this site. It goes to no third party, joins no mailing list, and fires no tracking. See the privacy policy.

Build progress

The unit mix, the permitted price and how far up it is

None of this table is the developer’s account of itself. It is what the Ministry of Housing and Local Government records from the 7(f) returns: unit type, bedrooms and bathrooms, built-up area, unit count, the price range on the permit, and the certified percentage complete. A brochure price can be revised; the price on the permit was filed. A brochure need not mention progress; the percentage is certified. The status vocabulary is theirs too: Lancar (on schedule), Lewat (behind), Sakit (sick), Terbengkalai (abandoned).

30807-1 · PANGSAPURI SERI JURU INDAH

Overall status: Lancar — on schedule

Certified completion by componentRumah Pangsa/Kondo – 148 units43.65%
ComponentBed / bathBuilt-upUnitsPrice on the permitComplete
Rumah Pangsa/Kondo
23 storeys
Lancar
3 / 2—148RM462,000.00
– RM554,000.00
43.65%

Swipe the table sideways for the rest of the columns.

The filed advertisement · on the ministry’s own server

This is the document the developer had to file, and the housing department had to approve, before it was allowed to advertise at all — served from the ministry’s own host. It normally carries the location plan, the developer licence and building-plan approval references, the expected completion date, the encumbrance position, and the unit count and price floor and ceiling for each type. The brochure a salesperson hands you can be reissued. This one cannot.

Open the filed advertisement (PDF)

Read from teduh.kpkt.gov.my on 2026-10-08, project code 30807-1. Re-read weekly.

What to do with the number. Read it against the delivery date in your own agreement, not against what a salesperson says. A project with a year left on its statutory clock and a third of the building up is telling you something the brochure will not.

How does that compare? Every development on this site, grouped by register status — cancelled, abandoned and behind schedule first.