Aricia Residences @ Sungai Besi
Two documents filed with the Ministry of Housing say this building will be finished in November 2027. The developer’s own website says September 2029. That is a gap of roughly 22 months between the developer’s two statements of completion, and it is the first thing on this page because it is the most important thing about it.
I answer myself. Louis Koh, Director, LK Group Marketing · IQI Realty Sdn Bhd · Registered Estate Agency.



Aricia Residences at a glance
Every line below is taken from a named published source, and where two published sources disagree both are shown. The two statutory filings are the KPKT filed advertisement brochure and the KPKT filed newspaper advertisement, both under licence/phase 30632-1.
- Expected completion — as filed
- November 2027Printed in BOTH statutory filings — the brochure and the newspaper advertisement.
- Expected completion — developer’s own website
- September 2029Footer of every page of aricia.com.my; aricia.my says “Estimated 2029”. Roughly 22 months later than the filings.
- Licensed developer
- Aricia Sdn Bhd (612583-A)The licensee named in the filing. A single-purpose company, NOT “Chin Hin Property Development” as PropertyGuru and vivahomes state.
- Developer’s licence
- 30632/11-2028/0307(A) · valid 28/11/2023 – 27/11/2028Filed. This is the LICENCE validity. It is not the APDL validity and this page never presents it as one.
- APDL — the government copy
- xxxxx-x/xx-xxxx/xxxx(x)-(x)Filed as a literal placeholder, with validity also printed as
xx/xx/xxxx – xx/xx/xxxx. Lapse-versus-current therefore CANNOT be assessed from the filing. - APDL — the developer’s microsite
- 30632-1/01-2028/0076(N)-(S) · valid 25/01/2025 – 24/01/2028Printed on aricia.com.my. On its face current as at 7 October 2026. Source is marketing material, not the filing.
- Approving authority
- Dewan Bandaraya Kuala Lumpur · plan ref DBKL.BPS1OSC20242271(24)Filed, and repeated on the developer’s own statutory block. DBKL’s planning jurisdiction is the Federal Territory only — this is what settles the locality.
- Development type, as filed
- Pangsapuri Servis (serviced apartment)Filed, verbatim. Five residential unit types, all expressed as bedroom counts. No office suite, SOHO, SOFO or strata office parcel is disclosed by any source.
- Tenure
- Hak Milik Kekal — freeholdFiled. Sekatan Kepentingan: Tiada (no interest restriction). Beban Tanah: Tiada (no chargee disclosed at filing date).
- Land category, as filed
- Syarat Nyata: Komersial (commercial)Filed. Normal for a Kuala Lumpur serviced apartment, but commercial assessment rates and commercial utility tariffs follow from it. That is an outgoings question, not an HDA question.
- Units and storeys, as filed
- Blok A 438 units / 40 storeys · Blok B 349 units / 39 storeys · 787 totalFiled in both statutory documents. PropertyGuru says 49 and 46 storeys and “612 to 787 units”; myBina says “48 storey, 612 units”. Contested three ways — this page does not pick one.
- Filed sale and purchase agreement price range — Blok A
- RM530,000 – RM1,396,000Statutory filed advertisement particulars (Harga Jualan Unit, Minima – Maksima). Not a price list, not a quotation, not an offer.
- Filed sale and purchase agreement price range — Blok B
- RM713,000 – RM938,000Statutory filed advertisement particulars (Harga Jualan Unit, Minima – Maksima). Not a price list, not a quotation, not an offer.
- Foreign buyers
- Kuala Lumpur threshold RM1,000,000 with EPU consent — the whole of Blok B is below itDerived from the filed band: Blok B’s filed MAXIMUM is RM938,000. Only upper Blok A units reach the threshold.
- Layout types
- 4 in the filing (A1, B1, C1, D2) · 5 on the developer’s own site (A1, B1, C1, D1, D2)550 / 757 / 872 / 1,410 / 1,420 sq ft. The filing labels the 1,410 sq ft type “D2”; the developer calls it D1 and gives D2 as 1,420 sq ft.
- Car park, as filed
- 1 / 2 / 3 lots per unitA single global statutory field. The filing gives no per-type allocation; the developer’s aricia.my table does, and third parties disagree with it.
- Green certification
- GreenRE Silver — PROVISIONAL CERTIFICATION, 24 December 2024GreenRE public register, filed under Aricia Sdn Bhd, tool RES v3.3. The developer’s corporate page says “GreenRE (Silver) Certified Building”, which the register does not support.
- Land area, mukim, daerah, lot / PT
- NOT PRINTED by any sourceKeluasan Tanah is absent from the filing and from every developer document. There is no Federal Territory equivalent of Selangor’s eHartanah register. No density figure on this page is presented as published.
- Phases under this licence
- One — 30632-1Serial walk performed: 30632-2, 30632-3 and 30632-4 all return 404. No hidden phase and no second scheme under licence 30632.
- Site progress
- Developer publishes four site-progress photographs headed “As at September 2026”aricia.com.my. The photographs reproduced lower down this page are the developer’s own site-progress set held in our library under a July 2026 title.
Explore related topics
Where a term on this page is a legal or statutory one, it links to the glossary entry that defines it.
Six things about Aricia Residences that are worth knowing before you see a show unit
None of these is a criticism of the building. Each is a published fact, or a published gap, that a buyer is entitled to have in front of them — and each one came out of reading the government filing against the developer’s own material, line by line.
The developer gives two completion dates, 22 months apart
Both KPKT filings — the brochure and the newspaper advertisement — say November 2027. Every page of the developer’s own microsite footer says September 2029, and aricia.my says “Estimated 2029”. Agents and portals all carry 2029. Under a Schedule H agreement the date that binds is the one in YOUR sale and purchase agreement, and liquidated damages run from it. Read it there; do not rely on either figure above.
The APDL in the government copy is a blank placeholder
The statutory field for the APDL is filed as the literal string xxxxx-x/xx-xxxx/xxxx(x)-(x), with its validity as xx/xx/xxxx – xx/xx/xxxx. The field was uploaded unfilled. So whether the permit is current or lapsed cannot be assessed from the filing at all. The developer’s own microsite does print a real one — 30632-1/01-2028/0076(N)-(S), valid to 24/01/2028. Both facts are on this page.
Blok B is entirely closed to foreign buyers on price
Kuala Lumpur’s foreign-purchase threshold is RM1,000,000 with EPU consent. Blok B’s filed statutory MAXIMUM is RM938,000 — so no Blok B unit, at any size, reaches it. Only the upper end of Blok A, filed to RM1,396,000, clears the line. Not one source on this project mentions foreign eligibility at all, even though most of the stack falls below the threshold.
The licensee is a single-purpose company, and only one page says so
The licensed developer is Aricia Sdn Bhd (612583-A). PropertyGuru and vivahomes credit “Chin Hin Property Development”; the corporate site credits Chin Hin Group Property Berhad. The split is disclosed on exactly one page — aricia.com.my/term. And AmBank calls Aricia Sdn Bhd a subsidiary of Chin Hin Group Berhad, a different listed entity. Which one owns it is not published.
GreenRE Silver is PROVISIONAL, not certified
The GreenRE public register records: Aricia Residences, developer Aricia Sdn Bhd, PROVISIONAL CERTIFICATION, SILVER, tool RES v3.3, dated 24/12/2024. The developer’s corporate page calls it a “GreenRE (Silver) Certified Building”, dropping the qualifier. Provisional certification is awarded on design; it is not final as-built certification. Separately, no award belongs to this project — the group’s own awards page is a 404.
The developer publishes no rail distance at all
The whole pitch is “one MRT stop from TRX”, yet aricia.com.my/amenities has six amenity categories — retail, education, medical, recreation, highways — and no transport category. Third parties disagree with each other roughly two-fold, and PropertyGuru collapses the separate LRT and MRT stations into one “integrated” node. This page attributes every figure and estimates nothing.
What is actually being built, and what the two sets of documents say about it
The statistics band below is the filed set. Where the developer’s marketing or a portal gives a different number, the difference is stated rather than smoothed over.
Facilities, as the developer’s own numbered text schedule prints them
This is unusually good source material: aricia.com.my publishes a genuine numbered schedule as HTML text, not only as a graphic. Level 8 runs 1–20. Level 9 is numbered 21–28, which implies eight items — but only seven are named. One Level 9 item is unaccounted for, and this page does not pad the list to eight.
Level 8 — items 1 to 20
- 50m Infinity Swimming Pool
- Sunken Wet Lounge
- Jacuzzi
- Pool Deck
- Wading Pool
- Cabana
- Seating Lounge
- Covered Walkway
- Parcourse
- Reflexology Path
- Play Lawn
- Children’s Playground
- BBQ Deck & Dining Area
- Pre-Function Deck
- Pocket Garden
- Gymnasium
- Indoor Play Gym
- Badminton Court / Multi-Purpose Hall
- Hoop Court
- Nursing Room
Level 9 — numbered 21 to 28, seven named
- Music Lounge
- Outdoor Deck
- Games Room
- Co-Working Lounge
- Function Room
- Surau (Female)
- Surau (Male)
- — the eighth number in the developer’s own 21–28 range is not named anywhere
Published, but in neither numbered schedule
- Pet Zone — a gallery caption, a feature-strip icon (“Pet-Friendly Facilities”) and an image, yet absent from both the Level 8 and the Level 9 numbered lists
- Grand lobby and drop-off — named in the gallery, with no ground-level schedule published at all
Named only by third parties
- “9-Level Car Park” (chansowlin.my) — not developer-published, and hard to reconcile with facilities sitting on Levels 8 and 9
- “Grand Lobby & Drop-off Area” (chansowlin.my)
- “Basketball Hoop Court” (chansowlin.my) — the developer’s own word is “Hoop Court”
Two conflicts inside the published material
- Badminton or pickleball? The Level 8 text schedule, item 18, reads “Badminton Court / Multi-Purpose Hall”. The gallery caption for the same space reads “Multi-Purpose Hall / Pickleball Court”. Both are the developer’s own words on the developer’s own site.
- Which level? myrumahbaru puts the gymnasium, badminton court and nursing room on Level 9. The developer schedules all three on Level 8. PropertyGuru assigns no level at all.
- Nothing is marked “space only” by the developer, and no item is disclosed as a shell. Ask for that in writing anyway.
Unit and building specification, as published
- Smart Home System and digital door lock
- Inverter air-conditioners
- Kitchen cabinets with hood and hob, “Fitted by SIGNATURE” — a brand inside the Chin Hin group’s own stable, a relationship the developer does not disclose
- Multi-tier security with 24/7 CCTV
- Service charge, sinking fund and maintenance rate per sq ft: NOT PUBLISHED by anyone
- Lift count, lift-to-unit ratio, ceiling heights, visitor parking: NOT PUBLISHED
Dated milestones, each from a named source
Five marketed types, four in the filing — and a label that does not match
The filed statutory schedule lists four types: A1 550 sq ft, B1 757 sq ft, C1 872 sq ft and D2 1,410 sq ft. The developer markets five, and calls the 1,410 sq ft type D1, with D2 as 1,420 sq ft. So the filing’s “D2” carries D1’s built-up. One of the two is mislabelled, and the page shows both labels rather than choosing. Sizes are printed in the filing as “kps” (kaki persegi, square feet); no square-metre column exists in any source, so no sq m figure appears here.

Type A1 — 550 sq ft
The only type where the filing, aricia.com.my/serviced, aricia.my and PropertyGuru all agree: 550 sq ft, 1+1 bedrooms, 1 bathroom. The “+1” is a flexi or study room — chansowlin.my calls it “flexi” — but no source publishes a room-by-room schedule, so the +1 is not independently verifiable. This is not a studio office, SOHO or SOFO: it is filed as “1+1 Bilik Tidur / 1 Bilik Air”, residential. Floor plan published by the developer and labelled Type A1 on its own page (confirmed caption).
Ask for the A1 plan and stackType B1 — 757 sq ft
Filed at 757 sq ft with 2+1 bedrooms and 2 bathrooms, and marketed the same way. The car park count is the disagreement: the developer’s aricia.my table says 2, myrumahbaru says 1, and chansowlin.my says “2–3”. The filing gives only a global “1 / 2 / 3” statutory field and no per-type allocation at all, so none of the three can be checked against it. Note too that the April 2024 preview coverage describes the range as starting at 872 sq ft — this type is absent from that description.
Type C1 — 872 sq ft
This is where the developer contradicts itself. The filing says 2 bathrooms and 3+1 bedrooms. aricia.my says 3 bathrooms and 3 bedrooms. myrumahbaru and PropertyGuru both say 2 bathrooms, agreeing with the filing against the developer’s own second site. chansowlin.my calls it “3+1 (flexi)”. Count the bathrooms on the plan at the gallery, and have the figure confirmed in the sale and purchase agreement schedule.

Type D1 — 1,410 sq ft sky duplex
The duplex the project is built around — the feature strip reads “Duplex Living from 1,410 sq.ft.” The filing schedules this built-up under the label D2; the developer labels it D1 on aricia.com.my/duplex and on aricia.my. Both the group’s press material and AmBank describe these as “the first-ever 3-bedroom sky duplexes in the Sungai Besi area” — a self-scoped claim with no registry definition of “sky duplex” and no independent support, so it is attributed here and not repeated as fact. Plan published by the developer and labelled Type D1 (confirmed caption).
Ask for the duplex plan and stackType D2 — 1,420 sq ft
The developer’s aricia.my table and chansowlin.my both list a D2 at 1,420 sq ft. The filed statutory schedule does not contain a 1,420 sq ft type at all — it uses the label D2 for the 1,410 sq ft unit. PropertyGuru sidesteps the problem by printing “1,410–1,420” as one range. If you are buying this type, get the label, the built-up and the plan written into the sale and purchase agreement schedule, because the filed advertisement will not corroborate them.
Unit count per type
The filing gives the block split — 438 in Blok A, 349 in Blok B — and nothing more. No source anywhere breaks the 787 units down by type, so the actual supply of duplexes, and of the 550 sq ft type, is unknown from published material. chansowlin.my adds “Tower A: 15 units per floor, Tower B: 9 units per floor”, and the arithmetic only half closes: 349 ÷ 9 = 38.8 against a filed 39 storeys, which works, but 438 ÷ 15 = 29.2 against a filed 40, which does not. Treat the per-floor figures as unverified.
Layout sizes above are the filed statutory schedule and the developer’s own published tables, with every disagreement named. Floor plans are reproduced only where the developer publishes one and labels it. Where no plan is published, the space says so — nothing is substituted and no subject is captioned that cannot be sourced. All built-ups are approximate and subject to final survey; the governing figures are those in the sale and purchase agreement and its schedules.
The developer’s own renders, with the developer’s own captions





























Every image on this page comes from the licensed developer’s own published material — aricia.com.my and its layout, facilities and gallery sections. Captions marked confirmed reproduce the caption the developer publishes beside the image; captions marked confirmed by position take their subject from the labelled section the image sits in. No image subject on this page is inferred from a filename alone, and no stock photograph has been substituted. All renders are artist’s impressions. The developer’s own disclaimer reads: “All renderings are artist’s impressions only. All measurements are approximate… subject to variations, modifications and substitutions as may be required by the Authorities.” The developer also publishes a 360° virtual tour.
Ask me for the full developer gallery and e-brochureJalan Sungai Besi, Chan Sow Lin corridor, Kuala Lumpur
One site, and four different locality labels in circulation. The locality is settled not by a portal field but by the filing: both the filed brochure and the filed newspaper advertisement name the approving authority as Dewan Bandaraya Kuala Lumpur, with building-plan reference DBKL.BPS1OSC20242271(24). DBKL’s planning jurisdiction runs to the Federal Territory of Kuala Lumpur and nowhere else. The developer’s own statutory block repeats the same authority and the same reference on every page of its microsite.
The map pin is set to the street address published by the developer and by PropertyGuru (“304, 302, Jalan Sungai Besi, 57100, Kuala Lumpur”). No GPS coordinate for the site is published anywhere. The only coordinates the developer publishes belong to its sales gallery in Chow Kit, several kilometres away, and are not reproduced here as the project’s location — StarProperty makes exactly that mistake and prints the sales gallery address as the project address. There is also no Federal Territory equivalent of Selangor’s eHartanah public register to check a coordinate against.
Rail — and why there is no single number here
- The developer publishes no rail distance at all. aricia.com.my/amenities carries six categories — Retail Destinations, Educational Institutions, Medical Care, Recreational Area and Highways — and no Transportation, LRT or MRT heading, even though the page’s own meta keywords mention “LRT”.
- Chan Sow Lin LRT (Sri Petaling Line): 0.88 km per myrumahbaru; about 1.3 km per chansowlin.my. Roughly a two-fold disagreement.
- Chan Sow Lin MRT (Putrajaya Line): 1.0 km per myrumahbaru; about 1.6 km per chansowlin.my.
- PropertyGuru collapses the two into one node — “integrated Chan Sow Lin LRT and MRT station”, 1.3 km. They are two separate stations with an interchange link, and this page keeps them separate.
- Connectivity claims, attributed and not measured: “just one MRT station away from TRX development” (Business Today / EdgeProp, April 2024); “MRT → TRX (1 stop) → Conlay (2) → KLCC (3)” (chansowlin.my, agent).
- No distance is published by anyone to Sungai Besi LRT or MRT station, Bandar Tasik Selatan / TBS, KL Sentral, KLIA or klia2, or any named bus stop. No source publishes a drive time in minutes for anything. This page does not estimate one.
Highways — developer figures, with the agent’s disagreement noted
- MEX Expressway / SALAK Expressway — 3.0 km (developer)
- Sungai Besi Expressway — 3.0 km (developer); chansowlin.my says 5 km
- MRR2 — 5.0 km (developer); chansowlin.my says 7–8 km
- Federal Highway — 7.0 km (developer)
- AKLEH — 7.0 km (developer)
Retail, as the developer publishes it
- Viva Mall 2.3 km · IKEA Cheras 2.4 km · AEON Mall Taman Maluri 2.4 km
- MyTown Shopping Centre 2.7 km · Sunway Velocity Mall 2.8 km · LaLaport BBCC 3.4 km
- Berjaya Times Square 3.8 km · The Exchange TRX 4.3 km · Sungei Wang Plaza 4.7 km
- Merdeka 118 4.9 km · Lot 10 5.0 km · Fahrenheit88 5.8 km
- Pavilion KL 5.8 km · KL Tower 5.8 km · Suria KLCC 6.1 km
- Mid Valley Megamall 6.3 km · The LINC KL 6.5 km · Avenue K 7.0 km
- The Gardens Mall 7.3 km · Intermark Mall 7.4 km · EkoCheras Mall 9.5 km
Education, as the developer publishes it
- Imperium International College 1.4 km · Sunway College @ Velocity 2.6 km
- Alice Smith International School 3.0 km · SJK(C) Chung Kwo 3.1 km
- BERJAYA University College 3.9 km · Tsun Jin High School 4.0 km
- Kuen Cheng High School 4.4 km · INTI International College 4.6 km
- Taylor’s International School KL 5.0 km · SEGi College KL 5.2 km
- SJK(C) Confucian 5.4 km · SM Teknik Kuala Lumpur 5.7 km
- St. John’s International School 5.8 km · SMK Convent Bukit Nanas 5.9 km
- Sayfol International School 7.4 km · UTM 8.5 km · Universiti Malaya 10 km
Medical and recreation, as the developer publishes it
- Sunway Medical Centre Velocity 3.7 km · Tung Shin Hospital 4.9 km
- Prince Court Medical Centre 5.4 km · UKM Specialist Children’s Hospital 6.4 km
- Pantai Hospital Cheras 6.8 km · Pantai Hospital Ampang 7.0 km · Kuala Lumpur Hospital 8.0 km
- Pantai Hospital Kuala Lumpur 9.1 km · University Malaya Medical Centre 9.6 km
- KPJ Ampang Puteri Specialist 10.4 km · Gleneagles Hospital 10.8 km
- Royal Selangor Golf Club 4.4 km · KLCC Park 5.1 km · Permaisuri Lake Garden 5.2 km
- KL Forest Eco Park 6.1 km · ASEAN Sculpture Garden 7.8 km · Ampang Hilir Lake Garden 8.2 km
- Perdana Botanical Garden 8.4 km · Ketumbar Hill 8.4 km · Titiwangsa Lake Garden 10.7 km
Four locality labels for one site — and two that are simply wrong
- Sungai Besi — the developer, the April 2024 press and AmBank.
- Chan Sow Lin — myrumahbaru (in its URL and its label) and vivahomes.
- Cheras — PropertyGuru’s district field, and the concept text on the developer’s own microsite.
- “Selangor” — mydreamproperty.com.my and newpages.asia both tag the project “Kuala Lumpur (KL), Selangor, Malaysia”. That is false. It is a template artefact of those directories, and the DBKL approval settles it: this is a Federal Territory project, not a Selangor one. The distinction is not cosmetic — the foreign-buyer threshold and the consenting authority both change with it.
- An independent construction database, myBina, classifies the works as an “Apartment Suites construction project in W.P. Kuala Lumpur” — agreeing with the filing.
- Mukim, daerah, seksyen, lot and PT number: NOT PRINTED by the filing or by any other source located. This page does not name a mukim, because no document does.
Distances in the four amenity lists above are the developer’s own published figures from aricia.com.my/amenities, reproduced as kilometres because that is the unit the developer uses. Where an agent site gives a materially different figure for the same road, both are shown. Rail distances are third-party only, because the developer publishes none, and they are attributed individually. No distance, drive time or walking time on this page has been estimated, measured or converted by us.
BUTIR-BUTIR IKLAN — the filed advertisement particulars, licence/phase 30632-1
This is the spine of the page, not a footnote. Everything in the table is transcribed from the two documents the developer is required by law to file with the Ministry of Local Government Development (KPKT): the advertisement brochure and the newspaper advertisement, both retrieved from the HIMS folder files/30632/30632-1/. The Malay label is given as printed. Where a field was filed empty or as a placeholder, the table says so instead of filling it in. The developer’s own published completion date is set beside the filed one so you can see both.
| Nama skim / pemajuan | Pemaju (licensed developer) | No. Lesen Pemaju | Tempoh Sah Lesen | No. Permit Iklan dan Jualan (APDL) — as the government copy prints it | Tempoh Sah Permit — as filed | APDL — developer’s microsite | Pihak Berkuasa yang Meluluskan | Rujukan Pelan Bangunan | Jenis Pembangunan | Pegangan Tanah | Syarat Nyata | Sekatan Kepentingan / Beban Tanah | Jumlah Unit & Bilangan Tingkat | Tempat Letak Kereta | Tarikh Dijangka Siap — as filed | Expected completion — developer’s own website | Harga Jualan Unit — Blok A (filed sale and purchase agreement range) | Harga Jualan Unit — Blok B (filed sale and purchase agreement range) | Keluasan Tanah | Lot / PT / mukim / daerah / seksyen | Diskaun Bumiputera — the filed Bumiputera field |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| NOT PRINTED. The filing carries no nama skim or nama pemajuan heading at all. It opens straight into “Pelan Unit” and the particulars, identifying the development only by developer, licence number and DBKL plan reference. So unusually for a project of this kind there is no registered-versus-marketing name divergence to report — because no registered name was filed. | Aricia Sdn Bhd (612583-A) Filed address: A-0-9, Pusat Perdagangan Kuchai, No. 2, Jalan 1/127, Off Jalan Kuchai Lama, 58200 Kuala Lumpur. Tel 603-7984 7878. The microsite footer gives a different address — E-10-4, Megan Avenue 1, 189 Jalan Tun Razak, 50400 Kuala Lumpur — on the same telephone number. | 30632/11-2028/0307(A) | 28/11/2023 – 27/11/2028 This is the LICENCE validity. It is not the APDL validity, and nothing on this page presents it as one. | xxxxx-x/xx-xxxx/xxxx(x)-(x)Filed as a literal placeholder — the field was uploaded unfilled. Lapse-versus-current therefore cannot be assessed from the filing. The serial the developer publishes (30632-1) does match the HIMS folder the filing came out of, so this is the right phase with an empty field, not the wrong document. | xx/xx/xxxx – xx/xx/xxxxAlso a literal placeholder. | 30632-1/01-2028/0076(N)-(S) Validity 25/01/2025 – 24/01/2028, printed on aricia.com.my and its /serviced and /duplex pages. Taken at face value, current as at 7 October 2026. The source is the developer’s marketing site, not the government filing — so this row is attribution, not corroboration. | Dewan Bandaraya Kuala Lumpur DBKL’s planning jurisdiction is the Federal Territory of Kuala Lumpur only. This is what settles the locality. | DBKL.BPS1OSC20242271(24) Filed, and reprinted on every page of the developer’s own statutory block. | Pangsapuri Servis (serviced apartment) Five residential unit types, all expressed as bedroom counts (Bilik Tidur / Bilik Air). No pejabat, office suite, SOHO or SOFO parcel appears in the filing, and none is disclosed by any other source. | Hak Milik Kekal — freehold No lease expiry applies. | Komersial (commercial land category) Normal for a Kuala Lumpur serviced apartment, and a real outgoings issue: commercial assessment rates and commercial utility tariffs follow, with no residential-rate electricity or water. This is a tenure-and-outgoings question and it is not the same thing as an HDA question — see the sub-heading below. | Tiada / Tiada No interest restriction, and no chargee disclosed as at the filing date. No later charge is disclosed anywhere, and the security for the AmBank facility is not stated. | Blok A: 438 units, 40 tingkat Blok B: 349 units, 39 tingkat Total 787 Filed in both statutory documents, and the developer’s microsite footer and AmBank both give 787. Contested three ways by third parties: PropertyGuru says 49 and 46 storeys and “612 to 787 units”; myBina says “2 blocks 48 storey, 612 units”. 612 is plausibly an earlier approved scheme, but neither source says so. This page does not pick one. | 1 / 2 / 3 lots per unit A single global statutory field. The filing gives no per-type allocation; nothing in the unit schedule covers car parking. | Nov 2027 Printed in both statutory filings — the brochure says “Nov 2027” and the newspaper advertisement says “November 2027”. | Sept 2029 Footer of every page of aricia.com.my; aricia.my says “Estimated 2029”; chansowlin.my says “Q3 2029, approximately 56 months from SPA signing”; myrumahbaru says “2029, Q3”; PropertyGuru, vivahomes and EdgeProp all say 2029. Roughly 22 months later than the filed date. Under Schedule H the date that binds is the one in your own sale and purchase agreement, and liquidated damages run from it. | RM530,000.00 (Minima) – RM1,396,000.00 (Maksima) Statutory filed advertisement particulars — the filed sale and purchase agreement range. Not a price list, not a quotation, not an offer. | RM713,000.00 (Minima) – RM938,000.00 (Maksima) Statutory filed advertisement particulars — the filed sale and purchase agreement range. Not a price list, not a quotation, not an offer. Note the consequence for foreign buyers below: RM938,000 is the whole block’s filed ceiling. | NOT PRINTED. Keluasan Tanah is absent from the filing and from every developer document. See “density” below — it cannot be computed from any developer-published figure. | NOT PRINTED. No lot, PT, mukim, daerah or seksyen appears in the filing or in any other source located. There is no Federal Territory equivalent of Selangor’s eHartanah register to look one up in. | The field is present in the filing. The value is withheld on this page under the publishing rule set out below. The allocation, release mechanism and quota mechanics are not published anywhere by anyone — ask for them in writing. |
Transcribed from the two filed documents under licence/phase 30632-1 and read against each other. Where the two filings differ in wording they do not differ in substance: both give 438/40 and 349/39, both give the same two price bands, and both give November 2027. A serial walk on 30632-2, 30632-3 and 30632-4 returned 404 in each case, so licence 30632 carries one registered phase only — there is no hidden extra scheme and no undisclosed phase.
The two price ranges above are the Harga Jualan Unit, Minima – Maksima as legally filed — that is, the filed sale and purchase agreement price ranges. They are published here because they are public statutory filed particulars. They are not a price list, not a quotation and not an offer, they describe the scheme as filed and not any individual unit, and they may have been superseded. The real figures for a specific unit come from the dated developer price list and from the sale and purchase agreement itself at the sales gallery. Ask me and I will go and get both.
Foreign buyers: the whole of Blok B is below the Kuala Lumpur threshold
In the Federal Territory of Kuala Lumpur a foreign purchaser needs a minimum purchase price of RM1,000,000 and the consent of the Economic Planning Unit (EPU). Set that against the filed statutory bands and the consequence is precise. Blok B’s filed maximum is RM938,000, so the entire block sits below the threshold — no Blok B unit, at any size or on any floor, reaches it. In Blok A, whose filed band runs to RM1,396,000, only units at or above RM1,000,000 qualify, which in practice means the upper end of the stack; the 550 sq ft and 757 sq ft types cannot get there. Two further points a foreign buyer should have in front of them: a reduction in price works against you here, because the threshold is tested on the purchase price, so bringing a unit down can push it under RM1,000,000 and disqualify it outright; and EPU consent is a separate approval that is not automatic. Not one source located on this project mentions foreign eligibility at all — not the developer, not the portals, not the agents — even though most of the price stack falls below the threshold. Kuala Lumpur is also not Selangor: the Selangor Zone 1 and Zone 2 figure of RM2,000,000, and the Zone 3 figure of RM1,000,000 with state consent, do not apply to this project, which is why the two directories that mis-tag it “Selangor” are worth correcting rather than ignoring.
Why the APDL row says “cannot be assessed” rather than “current” or “lapsed”
The APDL is the permit that makes it lawful to advertise and sell a housing development, and checking whether it is current is normally the single most useful thing you can do with a filed advertisement. Here you cannot. The KPKT copy prints the permit number as the literal string xxxxx-x/xx-xxxx/xxxx(x)-(x) and its validity as xx/xx/xxxx – xx/xx/xxxx — the fields went up unfilled. That is a documented failure of the filing, not an inference. What we can do is three things, and the page does all three. First, record the placeholder for what it is. Second, print the number the developer itself publishes — 30632-1/01-2028/0076(N)-(S), valid 25/01/2025 to 24/01/2028, which on its face is current as at 7 October 2026 — while being explicit that the source is marketing material. Third, refuse the easy error: the developer’s licence is valid 28/11/2023 to 27/11/2028, and that date is not the APDL validity. Pages that quietly put the licence expiry in the permit row are wrong, and this one does not. Before you sign anything, ask to see the physical APDL and check the number and the expiry against what is above.
Price: why the only figures on this page are the two filed statutory bands — and what this page does not publish, and why
This page publishes the filed statutory price ranges and nothing else, and on this project that decision needed more care than usual. Four separate publishers carry a “from RM___” starting figure that sits BELOW the filed statutory minimum of RM530,000. The four are a major portal, a new-launch aggregator, an agent microsite — and, remarkably, the developer group’s own corporate page, which prints a sub-minimum figure with an unexplained asterisk. These are four distinct publishers, not one syndicated feed. The finding is that a parent company’s own website undercuts its own subsidiary’s filed statutory minimum. The figures themselves are withheld here, deliberately. On top of that, one of those four labels its range “SPA price before rebate” — rebate language on the face of the source — which means every third-party price figure on this project has to be treated as rebate-adjusted and therefore unpublishable, including the duplex figures, which disagree with each other type for type anyway. So: this page carries no discount, no rebate, no nett price, no promotion, no freebie, no incentive, no commission, no Bumiputera discount value, no rental-guarantee rate and no yield or ROI projection. That is a deliberate rule, not an oversight. The rule is simple — if a number is not the sale and purchase agreement price, it does not go on this page, and if we are not certain what a number represents, it is left out entirely. A consistency check that does pass is worth noting: AmBank gives the GDV as RM467 million which, across 787 units, implies an average near RM593,000 — comfortably inside the filed band, and a further reason to distrust the sub-minimum figures. No public government registry price band (NAPIC/JPPH or similar) was located for this project. For a current price on a specific unit, ask me: I will go to the developer and bring back the dated price list and the sale and purchase agreement.
Schedule H is expected here — and the commercial land category is a different question
Two things get confused on serviced apartments and they are worth separating. On the HDA question the indicators are positive. The filed unit schedule contains five residential types only (A1, B1, C1, D1/D2), every one of them expressed in bedrooms and bathrooms; a direct read of the filing finds no pejabat, no office suite, no SOHO and no SOFO parcel; the developer holds a current HDA developer’s licence; an APDL was issued for this phase; and KPKT published the statutory advertisement — which is the licensing chain used for HDA housing accommodation. On that basis Schedule H is what you should expect, with its statutory defect liability period and its liquidated-damages mechanism. State it positively, then get it in writing: no source states, unit by unit, whether Schedule H or Schedule G is used, how long the defect liability period runs, or what the LAD basis is. One piece of hygiene while you are at it — the “office suites” and “dual-key” wording circulating about “Chin Hin’s new launch” belongs to Dawn, KLCC, a different development unveiled at the same preview event. It is not Aricia, and this page does not carry it over. Separately, and not the same issue: the land is filed Syarat Nyata: Komersial. That is normal for a Kuala Lumpur serviced apartment, but it means commercial assessment rates and commercial utility tariffs, with no residential-rate electricity or water — a real and recurring cost. Budget for it. It is an outgoings issue, not an HDA one, and conflating the two helps nobody.
Density, build percentage and site progress — what can and cannot be computed
Density cannot be computed from any developer-published figure, because no developer source publishes a land area. Keluasan Tanah is NOT PRINTED in the filing, and it is absent from aricia.com.my, from aricia.my and from the corporate project page. The only figure in circulation is 2.615 acres, carried by PropertyGuru, chansowlin.my and StarProperty — three publishers whose identical three-decimal figure and near-identical wording suggest one origin recycled rather than three independent measurements. If that figure were right, 787 units across 2.615 acres would be about 301 units per acre: a high-density tower project. We show the arithmetic so you can see what the third-party number implies, and we present it as third-party, not as published by the developer. Note that the developer makes no “low density” claim — correctly, since 301 units per acre would not support one — and this page will not introduce one. On build percentage: no figure is published by anyone. What the developer does publish is four site-progress photographs headed “As at September 2026”, which is evidence of activity and not a percentage. The construction database myBina holds the main contractor name and contract sum behind a paywall (“Main Contractor: Awarded”, project value “between 50 and 100 million” — a construction value, well below the RM467m GDV, and not a unit price), and no Bursa contract announcement for this project was located. The architect, C&S and M&E engineers and quantity surveyor are all paywalled too: myBina says 16 companies across 14 roles are on record and names none of them.
Not published, therefore not on this page — the list I will go and ask for
Every item here is a question a buyer would reasonably ask that no source answers. The land: lot or PT number, mukim, daerah, seksyen; the land area; any GPS coordinate for the site (the only coordinates the developer publishes are its Chow Kit sales gallery’s). The filing: the registered scheme name (none was filed); the APDL number and validity from the filing itself (placeholder only); the chargee or financier of the land beyond “Beban Tanah: Tiada” at filing date. The building: how many units of each layout type; the number of car-park levels and the visitor-parking provision; the lift count and lift-to-unit ratio; ceiling and floor-to-floor heights; the ground-floor facilities schedule and whether any retail or commercial parcel exists; the eighth item in the developer’s own Level 9 list. The money: the service charge and maintenance rate per sq ft, and the sinking fund — none of it published by anyone; whether any unit is sold furnished, and the fit-out specification beyond the four marketed items. The legals: whether Schedule H or Schedule G applies, the defect liability period length and the LAD basis; the Bumiputera allocation and its quota mechanics; foreign-buyer eligibility, which not one source mentions. The parties: which entity actually owns Aricia Sdn Bhd; the main contractor and contract sum; the architect and consultants; and the management company for the completed building — “Maplehome” is named as a maintenance and housekeeping partner in the April 2024 press, with no scope, term or appointment published. Certification: any as-built GreenRE certification (only provisional exists), and GBI status (no registry entry, and no claim made). Transport: any rail distance from the developer, and any distance at all to Sungai Besi station, TBS, KL Sentral or KLIA. Ask me for any of these and I will put the question to the developer in writing rather than guess at it.
Aricia Sdn Bhd (612583-A) — and the three different companies other people credit
The licensed developer of Aricia Residences, exactly as the KPKT filing prints it, is Aricia Sdn Bhd (612583-A). It is a single-purpose company named after the project. That matters because a buyer’s sale and purchase agreement is with the licensee, the HDA licence is held by the licensee, and any claim under the defect liability period is made against the licensee — not against whatever brand appears on the hoarding.
The brand almost everyone credits is Chin Hin, and they do not agree on which Chin Hin. PropertyGuru and vivahomes name “Chin Hin Property Development”, which is not a correctly stated legal name at all. PropertyGuru’s body text says “developed by the reputable Chin Hin Group”. The corporate project page sits on Chin Hin Group Property Berhad, which prints its own registration as “201001017677 (553434-U)”. And AmBank’s own announcement describes Aricia Sdn Bhd as a subsidiary of Chin Hin Group Berhad — the Bursa-listed building-materials parent, a different listed entity from Chin Hin Group Property Berhad. klpropertytalk and chansowlin.my get the licensee right.
The split is disclosed in exactly one place: aricia.com.my/term, which says the site is “owned and operated by CHGPB” while naming Aricia Sdn Bhd as the developer. That is the pattern across this whole series of pages — the licensee’s real identity hides on the terms page, never on the landing page. The group does have a cross-holding history, with Chin Hin Group Berhad having completed the acquisition of a 50.8% stake in Chin Hin Group Property Berhad in 2021, so both statements can be partly true at group level. But no source states which entity holds the shares in Aricia Sdn Bhd, so the ultimate holding company is recorded here as NOT PUBLISHED rather than guessed at. One smaller thing worth a second look if you are checking the corporate chain yourself: a new-format registration number beginning 201001 normally pairs with an old number issued around 2010, and numbers in the 553xxx band are typically 2001 incorporations — so the pair “201001017677 (553434-U)” is worth verifying against SSM before anyone reproduces it. Chin Hin Group Property Berhad is the former Signature International Berhad.
No joint-venture partner and no equity split is published by anyone. The project appears to be wholly developed through the Aricia Sdn Bhd vehicle. On financing, AmBank Group names Aricia Sdn Bhd in an RM307 million facility to Chin Hin group subsidiaries, and gives the project GDV as RM467 million; the portion of that facility attributable to Aricia is not broken out.
A related-party point the developer does not disclose. The microsite advertises “Kitchen Fitted by SIGNATURE” as a selling feature, presented in the way an independent premium supplier would be. SIGNATURE is a kitchen-cabinet brand within the Chin Hin group’s own stable. That is not a criticism of the cabinets — it is simply an in-house group fit-out rather than a third-party brand endorsement, and the relationship is not disclosed on the page that makes the claim.
Green certification: provisional, and the corporate site overstates it. The GreenRE public register records the project as Aricia Residences, developer Aricia Sdn Bhd, status PROVISIONAL CERTIFICATION, rating SILVER, tool RES v3.3, dated 24/12/2024. The developer’s own feature strip reads “GreenRE Certified Building (Silver Provision)”, which is close but leads with the word Certified; the corporate page goes further and says “GreenRE (Silver) Certified Building”, dropping the qualifier entirely. The register says provisional. Provisional certification is awarded on design and is not final as-built certification — the as-built award, if it comes, comes later and is a separate assessment. On GBI, no registry entry was located and the developer makes no GBI claim, so treat it as not GBI-certified (noting the search was not exhaustive).
Awards: none belongs to this project. The microsite has no awards section and names no award, and the group’s own awards page returns a 404. Other projects by the same group do carry recognitions in circulation — Botanica Hills, Divine KLCC, The NeX, Crown Penang, Amberwood, Ayanna, Avantro and Solarvest Suites among them — and not one of them belongs to Aricia Residences. No FIABCI, StarProperty, EdgeProp Best Managed, iProperty or PropertyGuru award is claimed for this project, and nothing on this page describes an “award-winning” development.
What the developer says about the project, in its own words. “Nestled within 4km of Kuala Lumpur’s vibrant heart, Aricia is an exquisite high-rise property inspired by the delicate beauty of butterflies… Its strategic location makes it a desirable residence, combining elegance with convenience and connectivity.” The feature strip reads: Freehold Residence · Strategic Location · Smart Home System · Duplex Living from 1,410 sq.ft. · Family-Friendly Residences · Pet-Friendly Facilities · GreenRE Certified Building (Silver Provision). Several of those are brochure adjectives with no factual content, and two are worth naming: “Strategic Location” is a connectivity claim from a developer that publishes no station distance at all, and “the first-ever 3-bedroom sky duplexes in the Sungai Besi area” (repeated by AmBank with “freehold” added) is self-scoped — “the area” is undefined, “sky duplex” has no registry definition, and no source substantiates a first. Attributed here; not repeated as fact.
Company names, registration numbers, licence and permit identifiers above are reproduced from the KPKT filing, the GreenRE public register, the developer’s own published material and the financier’s own announcement, each linked at the point of use. Where two published sources disagree, both are shown and the disagreement is named. Where nothing is published, this page says NOT PUBLISHED rather than filling the gap. The developer’s own disclaimer applies to all of its material quoted here: “The information contained in this material is subject to change and cannot form part of an offer or contract… All measurements are approximate.”
Aricia Residences @ Sungai Besi — frequently asked questions
When will Aricia Residences actually be completed?
Is the APDL current?
xxxxx-x/xx-xxxx/xxxx(x)-(x) and its validity as xx/xx/xxxx – xx/xx/xxxx — the fields were uploaded unfilled. The developer’s own microsite does print a real one: 30632-1/01-2028/0076(N)-(S), valid 25/01/2025 to 24/01/2028, which taken at face value is current as at 7 October 2026. Both facts belong on the page and both are on it. One trap to avoid: the developer’s licence runs 28/11/2023 to 27/11/2028, and that is not the APDL validity. Ask to see the physical permit and check the number and expiry yourself.Can a foreign buyer purchase at Aricia Residences?
What does it cost?
Why does this page not show any discount, rebate or nett price — and what else does it leave out?
Who is the developer — Chin Hin, or someone else?
How many storeys and how many units are there?
Is Aricia Residences freehold, and is it on commercial land?
Will I get a Schedule H sale and purchase agreement?
Is it GreenRE certified?
How far is the Chan Sow Lin station?
Is this a low-density development?
How many layout types are there, and which label is right?
What facilities are there, and which level are they on?
Is this project in Kuala Lumpur or Selangor?
Is there more than one phase, or a second Aricia somewhere else?
30632-1 — no hidden extra scheme and no undisclosed phase. Whether a later phase is planned is not stated anywhere. And no second development called Aricia exists elsewhere in Malaysia: deliberate searches in Penang, Johor, Selangor and Perak returned only this Sungai Besi project, and every domain carrying the name resolves to it. Note one genuine confusion risk: Dawn, KLCC was unveiled at the same preview event in the same press releases and is a different development — several of the built-up figures and the “office suites” and “dual-key” wording floating around for “Chin Hin’s new launch” belong to Dawn, not to Aricia.Want the filed documents and a current, dated price?
I will send you the two KPKT filings this page is built on, the developer’s own floor plans and facilities schedule, and a dated price list from the developer — and I will put the questions in the “not published” list to them in writing rather than guess at the answers.
Marketing information only. This page is not an offer, not a quotation and not a price list. All figures, dates and particulars are reproduced from the published sources linked throughout and are subject to change. The governing documents are the developer’s own price list, the sale and purchase agreement and its schedules, and the approvals held by the licensed developer.
Louis Koh
Director, LK Group Marketing · IQI Realty Sdn Bhd · Registered Estate Agency
I have spent over a decade selling property in Kuala Lumpur and Johor Bahru, and I build these pages the way I would want one built for me: the filed statutory particulars first, every hard number tied to a named published source, and the gaps printed as gaps. On Aricia Residences that method found a 22-month disagreement between the developer’s own two statements of completion, a permit field filed blank, and an entire block priced below the Kuala Lumpur foreign-buyer threshold. If something here is wrong, tell me and I will correct it. If something is missing, it is missing because nobody published it — ask me and I will go and get it.
Published 7 October 2026 · Last verified 7 October 2026 against the KPKT HIMS filings (licence/phase 30632-1), the GreenRE public register, the developer’s own microsites and corporate page, the financier’s announcement and the portals named above. Marketing information, not an offer.
Ask a specific question
If you would rather not use WhatsApp, use this. I answer them myself. Only your name and one contact method are required.
Developer: Chin Hin Group Property (7 developments on this site)
Where it is: Sungai Besi, Kuala Lumpur (KL)
The unit mix, the permitted price and how far up it is
None of this table is the developer’s account of itself. It is what the Ministry of Housing and Local Government records from the 7(f) returns: unit type, bedrooms and bathrooms, built-up area, unit count, the price range on the permit, and the certified percentage complete. A brochure price can be revised; the price on the permit was filed. A brochure need not mention progress; the percentage is certified. The status vocabulary is theirs too: Lancar (on schedule), Lewat (behind), Sakit (sick), Terbengkalai (abandoned).
30632-1 · RESIDENSI ARIS
Overall status: Lancar — on schedule
| Component | Bed / bath | Built-up | Units | Price on the permit | Complete |
|---|---|---|---|---|---|
| Pangsapuri Servis 40 storeys Lancar | 1, 3 / 1, 2, 3 | — | 438 | RM530,000.00 – RM1,396,000.00 | 37.50% |
| Pangsapuri Servis 39 storeys Lancar | 2, 3 / 2 | — | 349 | RM713,000.00 – RM938,000.00 | 47.56% |
Swipe the table sideways for the rest of the columns.
This is the document the developer had to file, and the housing department had to approve, before it was allowed to advertise at all — served from the ministry’s own host. It normally carries the location plan, the developer licence and building-plan approval references, the expected completion date, the encumbrance position, and the unit count and price floor and ceiling for each type. The brochure a salesperson hands you can be reissued. This one cannot.
Read from teduh.kpkt.gov.my on 2026-10-17, project code 30632-1. Re-read weekly.
What to do with the number. Read it against the delivery date in your own agreement, not against what a salesperson says. A project with a year left on its statutory clock and a third of the building up is telling you something the brochure will not.
How does that compare? Every development on this site, grouped by register status — cancelled, abandoned and behind schedule first.