M Sinar @ Southville City
A freehold serviced apartment on 5.7 acres inside a 428-acre township you can already walk through. The current permit covers 500 units — 78 at RM270,000 and 422 at RM618,000 to RM643,000, two car park bays each, completion stated June 2028. Every unit sits far below Selangor's RM2 million foreign-buyer floor, so a non-citizen cannot buy here.
⚡ Typical reply within 15 minutes, 9am–10pm MYT · No obligation


M Sinar @ Southville City at a glance
Two rows above carry more weight than the rest combined. Tenure is freehold, which in a corridor where a great deal of stock is leasehold is a genuine and permanent advantage. And no unit is available to a foreign buyer: Selangor's Zone 1 minimum purchase price for non-citizens is RM2,000,000, the Sepang district is inside Zone 1, and the highest price on this project's advertising permit is RM643,000. Everything below is transcribed from the statutory notice on Mah Sing's own project site, or from its published floor plan and facilities panels.
- Development
- M Sinar @ Southville CityMarketed as park home living within the township
- Developer on the permit
- Southville City Sdn Bhd, 788149-TThe township company, part of Mah Sing Group Berhad
- Developer licence
- 13425/03-2028/0360(A)Valid 2 Mar 2023 to 1 Mar 2028
- Advertising permit
- 13425-8/05-2027/0477(A)-(S)Valid 31 May 2024 to 30 May 2027
- Tenure
- FreeholdRestriction of interest stated as nil on the permit
- Approving authority
- Majlis Perbandaran SepangBuilding plan MPSepang. 600-34/3/619(12) — Sepang district
- Site area
- 5.7 acresThe developer says 5.7; media reports say 5.77
- Units on the permit
- 500 — Phase 1, Block A78 Type A plus 422 Type B
- Type A
- 550 sq ft, 2 bedrooms, 1 bathroomLabelled Affordable Apartment on the permit, priced RM270,000
- Type B
- 868 sq ft, 3 bedrooms, 2 bathroomsPriced RM618,000 to RM643,000 in Block A
- Car parks
- Two bays for both typesUnusual generosity at the 550 sq ft price point
- Land encumbrance
- Hong Leong Investment Bank BerhadDisclosed on the statutory notice
- Expected completion
- June 2028Check the date written into your own agreement
- Foreign buyers
- No unit qualifiesZone 1 floor is RM2,000,000; the top price here is RM643,000
Explore related topics
Curated hubs, each with its own guide — not auto-generated tag archives.
Six things that decide whether M Sinar suits you
The case for this project is not the building. It is the 428 acres around it, part of which is already built and lived in. That is a rare position for a buyer, because it converts the usual guesswork into research you can do yourself in an afternoon. The case against it is also not the building — it is the same 428 acres, 150 of which Mah Sing has earmarked for data centres, and the fact that the current permit covers only half the towers that were announced. Both halves are below.
Foreign buyers: the gap is RM1.36 million and it does not close
Selangor sets a zoned minimum purchase price for non-citizens. Zone 1 covers Petaling, Gombak, Hulu Langat, Sepang and Klang, and Zone 2 covers Kuala Selangor and Kuala Langat; the residential minimum in both is RM2,000,000. Zone 3, being Hulu Selangor and Sabak Bernam, is RM1,000,000. This project's building plan was approved by Majlis Perbandaran Sepang, so Sepang district, so Zone 1. The top price on the permit is RM643,000. Non-citizens in Selangor are also limited to strata and landed-strata property, subject to a cap on foreign purchases as a share of the non-Bumiputera units in a scheme, and consent is obtained from the Selangor state land office rather than from the federal committee that handles Kuala Lumpur. There is also a separate state-wide threshold of RM3,000,000 for commercial and industrial property. None of it matters here, because the price fails first. Have a Malaysian conveyancing solicitor confirm the current land office circular before relying on any threshold.
You can underwrite this project with your own eyes
Southville City is not a masterplan on a board. Earlier phases are complete and occupied, the retail hub is trading, and Summit Park exists. That means the two numbers that usually have to be guessed — what these units will resell for and what they will rent for — can instead be looked up. Walk the completed phases on a weekday evening. Count how many balconies have laundry on them. Look at whether the shop lots are tenanted or papered over. Check whether the landscaping in the oldest phase is maintained or thinning. Then ask an agent, or ask me, for the transacted prices and achieved rents in those phases over the last twelve months. That data set is the closest thing to a real answer you will get about M Sinar, and it costs an afternoon.
The data centre next door is real, unfinished, and two-sided
Mah Sing earmarked 150 acres of Southville City for data centres and launched Mah Sing DC Hub @ Southville City in May 2024 with Bridge Data Centres as the first partner, on 17.55 acres for up to 100MW. A second agreement over 35.68 acres with 200MW followed in October 2024. In May 2025 the group disclosed that the first agreement had lapsed on expiry of its exclusivity period, with reports describing the group as seeking new partners. So this is a live, unsettled situation rather than a done deal. For a resident the near-term reality is construction traffic on township roads. The medium-term reality is a large utility draw that is a fair question to put to the state. And the thing not to do is assume a data centre generates the tenant demand a factory or a campus does — it does not, because the employment density is low. Ask, do not assume, and do not pay a premium today for capacity that has already lapsed once.
Two bays on a 550 sq ft unit is the sleeper feature here
The permit states two car park bays for Type A and two for Type B. On an 868 sq ft three-bedroom apartment that is normal. On a 550 sq ft two-bedroom unit at RM270,000 it is unusual, and it materially changes what that unit is worth. Southville City has its own expressway interchange and no rail station of its own, so a household here needs vehicles. A small unit with one bay serves a single person; a small unit with two bays serves a couple who both commute, or a small family, or a tenant who wants to sublet a room. That widens the tenant pool substantially for a unit at the entry price point. If you are buying to let, this is the specification line I would weight most heavily, ahead of the finishes.
One block, two price tiers, one sinking fund
The permit places 78 affordable apartments at RM270,000 and 422 apartments at RM618,000 to RM643,000 inside the same Block A. I think delivering the affordable quota within the project rather than in a separate cheaper block is the better social choice, and I want to say so plainly. But it has a practical consequence you should price in. One management corporation, one service charge and one sinking fund will be funded by households whose budgets differ by more than a factor of two, and service charge arrears are the mechanism by which well-designed buildings degrade. Two questions to ask, in writing. How is the service charge apportioned — flat per square foot across both tiers, or differentiated. And what collection rate has the developer assumed in setting the rate. The answers tell you more about the next fifteen years than the gym does.
The permit covers half of what was announced
When M Sinar was announced in 2024 the reported scheme was two 33-storey towers with 999 units and a gross development value of RM462 million. The current advertising permit covers Phase 1, Block A only: 78 Type A plus 422 Type B, totalling 500 units. Both descriptions can be true — Block B would be a second phase requiring its own permit — but only Block A is presently permitted, and any Block B specification quoted to you should be treated as provisional. This matters for two reasons. Your view may change when the second tower rises, so ask which stacks face the future Block B footprint. And your service charge base changes when 500 units becomes 999, usually for the better, but only once the second block is occupied rather than when it is announced.
The whole development, decoded
The number I keep coming back to is not the unit count or the price — it is two car park bays for a 550 sq ft two-bedroom apartment. Developers do not give away parking, and a 550 sq ft unit at RM270,000 receiving the same allocation as an 868 sq ft unit at RM643,000 is a deliberate decision. In a township with its own expressway interchange and no rail station of its own, parking is the utility that actually determines whether a small unit is lettable. Read the two-bay allocation as the single most valuable thing about the Type A product.
Two products in one block, and one phase that is not permitted yet
Type A — the affordable tier
The permit labels these Affordable Apartment, which is a regulated category rather than a marketing adjective. Seventy-eight units of 550 sq ft with two bedrooms and one bathroom, priced at RM270,000, inside the same Block A as the market-priced tier. In Selangor an affordable quota unit normally carries its own eligibility test administered by the state and its own restriction endorsed on the title, and I have deliberately not stated which scheme applies here because Mah Sing has not named it on the project site. If you are buying at this price point, that is the first question to ask and it should be answered in writing: which scheme, what the income and residency criteria are, and how long the restriction runs. Everything else about the unit — the two car park bays, the show unit tour, the shared facilities — is documented.
Type B — the market tier
This is the bulk of the building: 422 of the 500 permitted units, at 868 sq ft with three bedrooms and two bathrooms. The permit gives a tight band, RM618,000 to RM643,000, a spread of only RM25,000 across four hundred units. That narrow spread is genuinely informative. It tells you there is no premium tier hiding at the top, no penthouse level and no corner stack priced far above the rest — the pricing is essentially flat, and what differentiates two units is floor level and orientation rather than product. At 868 sq ft with three bedrooms, the rooms will be compact; that is the trade for the price and the parking. Mah Sing publishes a dimensioned drawing, a stack diagram and a 360-degree tour, so you can judge the proportions yourself before you visit.
Block B — announced, not yet permitted
The gap between what was announced and what is permitted is worth reading carefully. When M Sinar was unveiled in 2024 the reported scheme was two 33-storey towers with 999 units in total and a gross development value of RM462 million on a 5.77-acre tract. Mah Sing's own project site today describes 5.7 acres and its statutory notice covers Phase 1, Block A, with 500 units. Nothing here is contradictory — a second block would need its own advertising permit and its own price band — but it means Block B currently has no published unit count, no published sizes and no published price. If you buy in Block A, ask which stacks will face Block B when it rises, and ask whether the facilities deck is shared or duplicated. Both answers change what you are buying.
Twenty-six numbered items on the published facilities plan
Mah Sing publishes a single numbered facilities plan for M Sinar with twenty-six labelled positions. The list below is transcribed from it. Note that four of them are marked space only on the plan itself — the multipurpose hall, the kindergarten, the multipurpose room and the associated provisions. Space only means the room is provided and the fit-out is not. That is an honest disclosure by the developer and I have kept it visible rather than tidying it away.
Arrival, water and outdoor recreation
- Guard house and grand drop-off
- EV charging stations at the drop-off
- Swimming pool and kids pool with playslide
- Sundeck lounge, two positions
- Outdoor lounge, two positions
- Barbecue terrace and outdoor shower
- Children playground, play lawn and outdoor gym
- Garden walkway
Indoor and management spaces
- Lobby, two positions, and mail room, two positions
- Management office and meeting room
- Gym and games room
- Co-working space
- Ruang solat
- Toilet and changing room
Marked space only on the plan
- Multipurpose hall — space only
- Kindergarten — space only
- Multipurpose room — space only
- Space only means the room is built and not fitted out
- Ask who funds the fit-out and when
In the township, outside the project
- Summit Park — described as award-winning, opposite the site
- A 10-acre green sanctuary within the township
- A retail hub the group describes as carrying over 100 brands
- The township's own North-South Expressway interchange
- Multi-tier security and rainwater harvesting, per the developer
Where the project is now
All 2 M Sinar @ Southville City floor plans
Mah Sing publishes two layouts and full specifications for both, which is more than most launches manage: Type A at 550 sq ft with two bedrooms and one bathroom, and Type B at 868 sq ft with three bedrooms and two bathrooms. Each has a dimensioned drawing, a stack diagram showing where it sits on the floor plate, and a 360-degree show unit tour. The permit prices them at RM270,000 and RM618,000 to RM643,000 respectively. There is no third type in Phase 1.

Type A — 550 sq ft, two bedrooms, one bathroom
Get this floor plan
Type B — 868 sq ft, three bedrooms, two bathrooms
Get this floor planInside M Sinar @ Southville City















Where M Sinar @ Southville City sits
M Sinar sits inside Southville City, off Jalan Southville 2, 43800 Dengkil, Selangor. Mah Sing markets the township as Bangi and that is how buyers search for it, but the statutory notice names Majlis Perbandaran Sepang as the authority approving the building plan, which places the land in the Sepang district rather than Hulu Langat. For foreign-ownership purposes it makes no practical difference — Sepang and Hulu Langat are both Zone 1 in Selangor's guidelines — but if a solicitor or a bank asks you which district the property is in, the answer is Sepang.
Mah Sing publishes a Waze pin at 2.904760, 101.760774 for the Southville City Sales Gallery at Savanna Boulevard Retail, not a coordinate for the M Sinar plot itself. This map is therefore a name search. Drive into the township first and ask the gallery to walk you to the 5.7-acre parcel and to Summit Park opposite it, because the whole argument for this project is the township around it rather than the plot.
- Kuala Lumpur city centreabout 19 kmfigure published by Mah Sing for the township
- North-South Expresswaydirect access via the township interchangeSouthville City has its own interchange
- Universiti Kebangsaan Malaysia, UPM, UNITEN, UniKL MFI, GMInamed, not measuredfive of the ten institutions on the developer's list
- IOI City Mall, KIPMall Bangi, EVO Mall, De Centrum, AEON Nilainamed, not measurednine shopping destinations listed without distances
- An-Nur Specialist, Az-Zahrah, Serdang, KPJ Kajang, Putrajaya hospitalsnamed, not measuredsix hospitals listed without distances
- Summit Park and the township retail hubopposite the site, within the townshipthe developer describes the park as award-winning
- Southville City Sales Gallery2.904760, 101.760774the developer's own Waze pin; open 10am to 6pm
- Nearest rail stationnot publishedthe project site mentions KTM Komuter access without naming a station
Two permits, 999 units, and a three-times gap in construction progress
The National Housing Department register holds M Sinar under two project codes, both licensed to Southville City Sdn Bhd (13425) in Sepang.
| Project code | Advertising permit | Permit expires | Units | Bed / bath | Price band on the permit | Built | Status |
|---|---|---|---|---|---|---|---|
| 13425-8 | 13425-8/05-2027/0477(A)-(S) | 30 May 2027 | 500 | 2–3 / 1–2 | 78 units RM270,000 (single price) 422 units RM618,000 – RM643,000 | 61.4–65.4% | Lancar |
| 13425-9 | 13425-9/05-2029/0366(N)-(S) | 18 May 2029 | 499 | 2–3 / 1–2 | RM250,000 – RM513,000 | 20.00% | Lancar |
| Total | 999 | Licensed developer: Southville City Sdn Bhd (13425) | |||||
Swipe sideways to see the full table →
Read from teduh.kpkt.gov.my on 27 August 2026. Pull it yourself: teduh.kpkt.gov.my/semakan-status-kemajuan?kodProjek=13425-8
Which code you are buying decides when you get keys
13425-8 is around 63% built. 13425-9 is at 20%. Two permits, almost identical product, and roughly two years of construction between them. Ask which KPKT project code your unit sits under before you pay a booking fee — it is the difference between a building that is going up and one that has barely started.
The price bands differ too: the later phase is permitted RM250,000 to RM513,000, while the earlier one is not a single band at all — the register splits it into 78 units at a fixed RM270,000 and 422 units at RM618,000 – RM643,000, with nothing in between. A fixed price on a fixed count of units is the usual signature of an affordable allocation. Same development, different ceilings — and, inside the earlier phase, two different products.
Foreign buyers: this one is closed
The highest permitted price across both phases is RM643,000. Selangor’s minimum for a non-citizen buyer is RM2,000,000 for most property types. Nothing here comes close to the threshold.
Check the percentage yourself
Those figures are the developer’s own progress returns under the statutory 7(f) report. Note today’s reading, re-check before each progress payment your bank releases, and treat a percentage that has not moved between two payments as a written question.
About Southville City Sdn Bhd (Mah Sing Group)

The company on the permit is Southville City Sdn Bhd, 788149-T, registered at Wisma Mah Sing, Penthouse Suite 1, No. 163, Jalan Sungai Besi, 57100 Kuala Lumpur. Note what that company number tells you. This is not a fresh single-purpose vehicle incorporated to launch one tower — it is the township company, and it has been the entity behind Southville City since Mah Sing began building the 428-acre masterplan. That continuity is the most useful thing about buying here, and it is the reason this page is written the way it is.
Here is the argument, and it is different from the argument for any other Mah Sing project. When you buy a standalone tower on a bare plot, every number you are given is a projection. When you buy a parcel inside a township that is already partly built and occupied, almost nothing needs to be projected. Southville City has completed and inhabited phases you can drive through this afternoon. You can see how the landscaping has aged, whether the retail is trading or shuttered, how full the car parks are on a weeknight, and how the earlier management corporations are performing. Then you can look up what those earlier phases actually resell for and actually rent for, and use that instead of a brochure yield. No developer can stop you doing this, and almost nothing else you can do is as informative.
The second thing worth knowing is what Mah Sing is building next door, because it cuts both ways. In May 2024 the group launched Mah Sing DC Hub @ Southville City, earmarking 150 acres of the township for data centres, and signed a joint venture with Bridge Data Centres over 17.55 acres for up to 100MW. In October 2024 a second collaboration was announced over 35.68 acres with 200MW of planned capacity. Then in May 2025 the group disclosed that the first agreement had lapsed when its exclusivity period expired, and reports at the time described Mah Sing as seeking new partners for the site, with the second agreement running to 28 October 2025. Treat announced megawatts as intention rather than fact — one of these deals has already lapsed once.
What a data centre next door actually means for a resident. The honest version has three parts. Construction: years of heavy vehicle movements on township roads you will also be using. Utilities: large facilities draw significant grid power and water, and how that is provisioned is a matter for the state and the utility rather than for your management corporation, but it is a fair question to ask. And employment: data centres are capital-intensive and employ relatively few people for their footprint, so do not underwrite your rental demand on them the way you would on a factory or a university. The genuine upside is different and slower — infrastructure upgrades, road improvements and the kind of institutional attention that follows large capital projects into a township.
One structural feature of this particular building that deserves saying plainly. The permit puts 78 affordable apartments at RM270,000 and 422 apartments at RM618,000 to RM643,000 inside the same Block A. That is a deliberate Mah Sing pattern — the state affordable quota is delivered within the project rather than shunted to a separate cheaper block. Socially I think it is the better choice. Practically it means one management corporation, one sinking fund and one service charge shared between households whose budgets differ by a factor of more than two. Ask the developer how the charge is apportioned and what the projected collection rate assumption is, because in a mixed-tier building that is where the long-run risk sits, not in the specification.
Frequently asked questions
Can a foreigner or a Singaporean buy at M Sinar @ Southville City?
No. Every unit is far below the price at which a non-citizen may buy in this part of Selangor, so there is no application to make.
Selangor applies a zoned minimum purchase price to non-citizens buying residential property. Zone 1 covers the districts of Petaling, Gombak, Hulu Langat, Sepang and Klang; Zone 2 covers Kuala Selangor and Kuala Langat. The minimum in both is RM2,000,000. Zone 3, being Hulu Selangor and Sabak Bernam, sits at RM1,000,000.
M Sinar's statutory notice names Majlis Perbandaran Sepang as the authority that approved the building plan, which puts the land in the Sepang district and therefore in Zone 1. The highest price on the permit is RM643,000. The gap is more than RM1.35 million.
The other Selangor rules, for completeness. Non-citizens may acquire strata and landed-strata property only, so the category would have been right. A cap limits foreign purchases to a share of the non-Bumiputera units in a scheme. Consent is granted by the Selangor state land office, not by the federal committee that handles Kuala Lumpur. And commercial and industrial property carries a separate, higher state-wide threshold of RM3,000,000.
Two federal points that apply wherever a non-citizen buys in Malaysia. From 1 January 2026 a flat 8% stamp duty applies to non-citizens acquiring residential property, with the legislation naming serviced apartments and SOHO units specifically. Real property gains tax for a non-citizen is 30% within five years and 10% from the sixth year onwards, with no zero band. Note also that in Malaysian land law the term foreign interest includes Malaysian permanent residents.
State guidelines are policy and they are revised from time to time. If you are a non-citizen with a Selangor budget, message me and I will send you what actually clears RM2,000,000 in Zone 1, and you should have a Malaysian conveyancing solicitor confirm the current land office circular before committing.
Is M Sinar in Bangi or in Sepang? The address and the permit say different things.
Both, in different senses, and the distinction is administrative rather than physical.
Mah Sing markets Southville City as being in Bangi and writes its M Sinar page around that word, because Bangi is how buyers in this corridor search and think. The postal address of the township is 43800 Dengkil. And the statutory notice names Majlis Perbandaran Sepang as the authority approving the building plan, which means the land is administered by the Sepang municipal council and sits in the Sepang district.
None of these contradict each other. Township brand names, postcodes and district boundaries are three different systems and they overlap untidily all over the Klang Valley.
Does it change anything for a buyer? For foreign ownership, no — Sepang and Hulu Langat are both Zone 1 in Selangor's guidelines and the threshold is RM2,000,000 either way. For everyday life, the practical answer is the one you can test: drive from the site to wherever you actually go, at the hour you actually go, and ignore which council empties the bins.
Where it does matter is paperwork. Your assessment rates, your building plan approvals for any renovation, and your certificate of completion all run through Majlis Perbandaran Sepang. If a solicitor, a bank or an insurer asks which district the property is in, the answer is Sepang, not Hulu Langat.
I have catalogued the project under Bangi on this site because that is how it is marketed and searched, and said Sepang everywhere the legal answer matters. That seemed more useful than being pedantic in the navigation.
What is the difference between the RM270,000 units and the RM618,000 units?
Size, configuration, and — most importantly — who is allowed to buy them.
The specifications first. Type A is 550 sq ft with two bedrooms and one bathroom, priced at RM270,000 on the permit, 78 units. Type B is 868 sq ft with three bedrooms and two bathrooms, priced at RM618,000 to RM643,000, 422 units. Both receive two car park bays. Both are in the same Block A and share the same facilities deck.
The important difference is the label. The advertising permit calls Type A an Affordable Apartment. In Selangor that is a regulated category, not a marketing word: affordable quota units are administered by the state, carry an eligibility test covering citizenship, residency and household income, and normally carry a restriction endorsed on the title limiting resale for a period. Mah Sing does not name the specific scheme on the project site, so I am not going to name it either.
What that means in practice. If you are looking at Type A, your first question is not the finishes — it is which scheme governs it, what the income and residency criteria are, whether you qualify, and how long the resale restriction runs. Get all four in writing before you pay a booking fee, because the restriction affects your exit, not just your entry.
If you are looking at Type B, none of that applies and you are buying an ordinary market-priced apartment.
One thing worth saying plainly: on a per square foot basis the two tiers are not comparable and you should not use one to argue the other is cheap or expensive. A regulated price is not a market price.
Ask me and I will get the scheme name and the restriction terms from Mah Sing in writing.
Is it 500 units or 999?
Five hundred are permitted today. Nine hundred and ninety-nine was the announced scheme. I use the permit.
When M Sinar was unveiled in 2024, the reported plan was two 33-storey towers on a 5.77-acre tract, 999 units in total, with a gross development value of RM462 million. Mah Sing's own project site today says 5.7 acres and its statutory notice is explicit: Phase 1, Type A 78 units, Type B 422 units, Block A. That is 500.
Both statements can be true. A second block is a second phase and needs its own advertising permit with its own unit count, sizes and price band. None of that has been published, so I have written the page around Block A and flagged Block B as announced rather than permitted.
Three consequences for you, all practical. First, your view: ask for the site plan and identify which stacks will look directly at the Block B footprint, because those units are worth less than the sales chart implies today and more or less exactly the same in five years when the second tower is up. Second, your service charge: 500 units carrying a facilities deck costs more per household than 999 units carrying the same deck, so if Block B is genuinely coming, your charge should ease when it completes — but not before.
Third, and most usefully, ask whether Block A and Block B will form one management corporation or two, and whether the facilities deck is shared or duplicated. That answer shapes fifteen years of running cost.
Message me and I will ask all three of those questions and forward the written answers.
Should I worry about the data centre park in the same township?
You should understand it rather than worry about it, and you should not pay a premium for it.
The facts, in order. In May 2024 Mah Sing launched Mah Sing DC Hub @ Southville City, earmarking 150 acres of the 428-acre township for data centres, and signed a joint venture with Bridge Data Centres over 17.55 acres for up to 100MW. In October 2024 a second collaboration was announced covering 35.68 acres with 200MW of planned capacity. In May 2025 the group disclosed that the first agreement had lapsed on expiry of its exclusivity period, and reports at the time described Mah Sing as seeking new partners, with the second agreement valid until 28 October 2025.
So the honest status is: land earmarked, capacity announced, one agreement lapsed, outcome unsettled. Treat announced megawatts as intention.
The downside for a resident, stated plainly. Data centre construction means years of heavy vehicle movements on roads you will share. Large facilities draw substantial grid power and water; how that is provisioned is a matter for the state and the utility rather than your management corporation, but it is a legitimate question to raise at the sales gallery and to keep raising.
The upside is real but indirect. Large capital projects pull infrastructure upgrades, road improvements and institutional attention into a township. What they do not pull, in proportion to their footprint, is people — data centres are capital-intensive and employ relatively few staff. So do not underwrite your rental demand on the data centre the way you would on a university or a manufacturing park. The tenant base here remains the universities, the industrial estates and the KL commuter.
Practical step: ask which parcels are earmarked, how far they are from M Sinar, and what the access route for construction traffic will be. Then decide.
What is the maintenance charge, and why is it not on this page?
Because Mah Sing has not published it, and on a building like this an estimate would do you more harm than a blank.
Here is what determines it. The facilities plan carries twenty-six numbered items including a swimming pool, a kids pool with a playslide, an outdoor gym, an indoor gym, a games room, a co-working space, a management office, a meeting room and two lobbies, spread across a deck serving 500 units. Add lifts, security, landscaping and a 5.7-acre site to maintain.
Then add the structural feature specific to this building: 78 of the 500 units are at RM270,000 and 422 are at RM618,000 to RM643,000, and all of them fund the same sinking fund. Arrears in a mixed-tier building are the single biggest long-run threat to the facilities you are paying for, because a facility that cannot be funded gets closed rather than repaired.
So the two questions I would put in writing, before the finishes and before the view. What is the projected service charge and sinking fund rate per square foot, and is it flat across both tiers or differentiated. And what collection rate assumption underlies that rate.
One related point. Four items on the facilities plan are marked space only — the multipurpose hall, the kindergarten and the multipurpose room. Space only means the room is built and not fitted out. Ask who is expected to fund the fit-out and out of which budget, because if the answer is the management corporation, that is a call on your sinking fund in year one.
Message me and I will chase all of it. When Mah Sing releases a rate I will run the yield with you properly rather than guessing at it now.
M Sinar or Anja Residences at Bangi?
Freehold and a finished township on one side, a wider product range and a golf outlook on the other. Their completion dates are the same month, which makes them unusually comparable.
Both permits state June 2028. Both start at RM270,000 for an affordable-tier unit. After that they diverge.
Tenure is the sharpest difference and the one I would weight most. M Sinar is freehold with restriction of interest stated as nil. Anja is leasehold expiring 14 July 2093, roughly 65 years unexpired at handover. Over a twenty-year hold that difference shows up in what your eventual buyer can borrow, and therefore in what they can pay you.
Product range runs the other way. Anja's permit spans 571 to 1,582 sq ft with prices to RM1,111,000; M Sinar's Phase 1 offers 550 and 868 sq ft with prices to RM643,000. If you want something larger than three compact bedrooms, M Sinar Phase 1 does not have it.
Then the surroundings. M Sinar sits inside a 428-acre township with completed phases you can inspect, a retail hub, a 10-acre park and its own expressway interchange — and 150 acres earmarked for data centres. Anja sits beside a golf course with a claimed 80% of units enjoying the view, in a long-established town, as a standalone development rather than a phase of an inspectable masterplan.
For a non-citizen the comparison is moot: both are far below the RM2,000,000 Zone 1 threshold. For a Malaysian buyer, I would say freehold plus verifiable township data beats a leasehold golf view unless the view is what you are actually buying.
Tell me your budget, your holding period and whether you are buying to live in or to let, and I will put them side by side properly.
What do the Selangor market figures say about buying here?
They say the segment is competitive and that pricing here sits close to where the market actually clears, which is the healthier place to be.
The national valuation department's Selangor figures for the first quarter of 2026 show 3,745 unsold residential units, 2,407 completed and unsold serviced apartments, 1,904 newly launched units and an average secondary-market transacted price of RM559,935.
Take the 2,407 seriously. M Sinar is a serviced apartment on the permit and that overhang is in the same category. When this building completes in June 2028 it will hand over into a market that already carries completed, unsold serviced apartment stock competing for the same tenants.
Now read the RM559,935 against the price list. Type B at RM618,000 to RM643,000 sits modestly above the state's average secondary transacted price; Type A at RM270,000 sits well below it. Neither is priced as a luxury product being pushed into a mid-market state. That is a meaningfully better position than a launch priced at twice the state average.
The 1,904 newly launched units is the number I would track. Supply is still being added, and your competition in 2028 is not the building next door today but everything permitted between now and then within a fifteen-minute drive. In this corridor that includes whatever Block B eventually becomes.
How I would use all of this. Prefer the specification that widens your tenant pool — here that is the two-bay allocation — insist on the service charge in writing, and treat the freehold tenure as the durable advantage it is when everything else in an oversupplied segment is competing on price.
These figures are quarterly. Ask me for the current quarter before you rely on any of them.
What has Mah Sing not published for this project?
Six items, and every one of them is a blank on this page rather than an estimate.
One. The service charge and sinking fund rate per square foot, and whether it is flat across both price tiers.
Two. The name of the state affordable-housing scheme governing the 78 Type A units, its eligibility criteria and the resale restriction it endorses on the title.
Three. Any construction progress photographs. Mah Sing publishes a 3D walkthrough video, a 360-degree aerial and two show unit tours for M Sinar, but no dated site photographs. Progress reporting for this group sits inside its own app rather than on the public project site, which is a real difference from developers who publish quarterly. If site progress matters to you, ask for it explicitly and ask for it dated.
Four. Block B: unit count, sizes, price band and permit status.
Five. The storey count for each tower from the developer directly. The 33-storey figure comes from media reporting of the 2024 announcement, not from the statutory notice.
Six. Who funds the fit-out of the three facilities marked space only on the plan.
None of these are unreasonable requests. A sales gallery that answers all six in writing is telling you something useful about how the company handles the awkward questions, which is exactly the behaviour you want to know about before you commit to a building you will not see finished for two years. Message me and I will ask for all six at once.
Drive the township first, then ask me for the numbers
This is one of the few projects where the most useful thing you can do costs nothing and takes an afternoon: drive through the completed phases of Southville City, look at how they have aged, and then ask me what those phases actually resell and rent for. I will send you the transacted comparables alongside the current M Sinar price list, the service charge if Mah Sing has released it, and which stacks are still open in each type.
No buyer-side agent fee on developer launches
Louis Koh
11 years in Malaysian property · Johor Bahru & Kuala Lumpur new launches · English & 中文
I work with cross-border buyers from Singapore and with local investors. I'll tell you when a project isn't right for you — that's usually worth more than the brochure.
Published 2026-08-11 · Last verified 2026-08-11 against Southville City Sdn Bhd (Mah Sing Group)'s published project material. Unit availability, pricing and completion dates are set by the developer and subject to change. This page is marketing information, not an offer or a contract.
Ask a specific question
If you would rather not use WhatsApp, use this. I answer them myself. Only your name and one contact method are required.
The unit mix, the permitted price and how far up it is
None of this table is the developer’s account of itself. It is what the Ministry of Housing and Local Government records from the 7(f) returns: unit type, bedrooms and bathrooms, built-up area, unit count, the price range on the permit, and the certified percentage complete. A brochure price can be revised; the price on the permit was filed. A brochure need not mention progress; the percentage is certified. The status vocabulary is theirs too: Lancar (on schedule), Lewat (behind), Sakit (sick), Terbengkalai (abandoned).
13425-8 · M SINAR
Overall status: Lancar — on schedule
| Component | Bed / bath | Built-up | Units | Price on the permit | Complete |
|---|---|---|---|---|---|
| Pangsapuri Servis 33 storeys Lancar | 1, 3 / 1, 2 | — | 422 | RM618,000.00 – RM643,000.00 | 64.10% |
| Pangsapuri Servis 33 storeys Lancar | 2, 3 / 1, 2 | — | 78 | RM270,000.00 | 70.00% |
Swipe the table sideways for the rest of the columns.
This is the document the developer had to file, and the housing department had to approve, before it was allowed to advertise at all — served from the ministry’s own host. It normally carries the location plan, the developer licence and building-plan approval references, the expected completion date, the encumbrance position, and the unit count and price floor and ceiling for each type. The brochure a salesperson hands you can be reissued. This one cannot.
Read from teduh.kpkt.gov.my on 2026-10-17, project code 13425-8. Re-read weekly.
13425-9 · M SINAR
Overall status: Lancar — on schedule
| Component | Bed / bath | Built-up | Units | Price on the permit | Complete |
|---|---|---|---|---|---|
| Pangsapuri Servis 33 storeys Lancar | 2, 3 / 1, 2 | — | 499 | RM250,000.00 – RM513,000.00 | 20.00% |
Swipe the table sideways for the rest of the columns.
This is the document the developer had to file, and the housing department had to approve, before it was allowed to advertise at all — served from the ministry’s own host. It normally carries the location plan, the developer licence and building-plan approval references, the expected completion date, the encumbrance position, and the unit count and price floor and ceiling for each type. The brochure a salesperson hands you can be reissued. This one cannot.
Read from teduh.kpkt.gov.my on 2026-10-17, project code 13425-9. Re-read weekly.
What to do with the number. Read it against the delivery date in your own agreement, not against what a salesperson says. A project with a year left on its statutory clock and a third of the building up is telling you something the brochure will not.
How does that compare? Every development on this site, grouped by register status — cancelled, abandoned and behind schedule first.