RTS Link countdown: December trial runs, February 2027 target — a timeline for Johor Bahru buyers and tenants

The Johor Bahru–Singapore RTS Link aims to carry passengers from February 2027, once trial runs finish by 31 December 2026 and independent safety certification and approvals from both countries follow. Johor plans a December dry run. Tenants should avoid paying an early RTS premium; buyers should compare walking routes that exist today.
Key figures
- By 31 December: final system tests and trial runs (joint statement).
- Then: independent safety certification and approvals from both countries; passenger service targeted for February 2027.
- December: Johor dry run to assess passenger movements and public transport (state exco Mohamad Fazli, via paultan.org).
- Bukit Chagar station: a 25-minute target from station entry to platform, with 18 luggage scanners, 9 body scanners and 100 automated e-gates (The Edge).
- Capacity: up to 10,000 passengers per hour per direction; about five minutes per trip; around 4 km long; about 40,000 daily riders expected at the start.
- Singapore: more than 600 personnel took part in a multi-agency security exercise at Woodlands North on 11 to 12 November.
What happened
Infrastructure on both sides is substantially complete; what remains is testing, certification and approval. On 2 October the two governments set February 2027 as the target, subject to independent safety certification and regulatory approval.

In Malaysia, after a change at the transport ministry, the Johor government said on 12 November that it is keeping the February target and will run a dry run in December. The Edge's special report describes the station design: co-located immigration for both countries on different levels, aiming for about 25 minutes from entry to boarding.

Louis’s take: what it means for buyers
First, tenants should not rush into expensive long leases. Rents around Bukit Chagar may price in an RTS premium before and after opening. If you will commute to Singapore, consider a shorter first lease until real clearance times and fares are known.
Second, buyers should compare routes you can walk today. Many projects quote distances based on planned or unfinished link bridges. Our RTS page uses measured walking routes, so compare on that basis.

Third, count the whole commute, not just the five-minute ride: the walk to the station, the 25-minute entry-to-platform target, and the connection on the Singapore side.
Fourth, the date still depends on safety certification. February is a target, not a guarantee, so avoid basing a purchase on a specific opening month.
Names in English, Chinese and Malay
| English | 中文 | Bahasa Malaysia |
|---|---|---|
| Johor Bahru–Singapore Rapid Transit System (RTS Link) | 新柔捷运系统(RTS Link) | Sistem Transit Aliran Johor Bahru–Singapura (RTS Link) |
| RTS Operations Pte Ltd (RTSO) | RTS 营运公司(RTSO) | RTS Operations Pte Ltd |
| Ministry of Transport Malaysia | 马来西亚交通部 | Kementerian Pengangkutan Malaysia |
| Land Transport Authority (LTA), Singapore | 新加坡陆路交通管理局(LTA) | Land Transport Authority (LTA), Singapura |
| Bukit Chagar station | 武吉查卡站 | Stesen Bukit Chagar |
| Woodlands North station | 兀兰北站 | Stesen Woodlands North |
Frequently asked questions
When will the RTS Link open?
On 2 October 2026 the two governments said passenger service is targeted for February 2027, subject to independent safety certification and regulatory approvals from both countries.
How long is the trip from Bukit Chagar to Woodlands North?
About five minutes on the train. The Edge reports that Bukit Chagar station targets about 25 minutes from entry to platform, including screening and immigration for both countries.
Is the December dry run open to the public?
The Johor government has only said the December dry run will assess passenger movements and public transport arrangements; as of 24 November 2026 we have not seen an official announcement of public trial rides.
How much will the RTS fare be?
We could not find an officially announced fare at the time of writing. Singapore's transport ministry said on 4 November that usage will depend on factors including the fares set by the operator.
Sources
- LTA & Ministry of Transport Malaysia — joint news release: RTS Link service targeted for February 2027 · 2 Oct 2026
- paultan.org — Johor state govt will get RTS Link ready for February 2027 launch · 12 Nov 2026
- The Edge Malaysia — Special Report: Completing RTS Link's intricate journey · 16–22 Nov 2026 weekly
- The Straits Times — Multi-agency exercise at RTS Link Woodlands North station · 14 Nov 2026
- Ministry of Transport Singapore — Parliamentary reply on RTS Link ridership and certification · 4 Nov 2026
Related projects and guides
Written by Louis Koh (REN 28209, IQI Realty) from public reports, with his own analysis; this is not a reprint of the source articles. Every figure is linked to its source. Things can change after publication, so check the latest before you decide.
New launch projects worth a look
- Setia Sky 88 @ JB City Centre · Johor Bahru
- Jasmin @ Tamansari · Rawang
- Jesselton Twin Towers · Kota Kinabalu
- The Stallionz @ Ipoh · Ipoh
- Triuni Residences @ Batu Uban, Penang · Gelugor
- Accent Residences @ Seksyen 13, Petaling Jaya, Selangor · Petaling Jaya