RTS Link countdown: December trial runs, February 2027 target — a timeline for Johor Bahru buyers and tenants

Published 24 November 2026Louis Koh · REN 282092 min read

News graphic: RTS Link countdown with passenger service targeted for February 2027
⚡ The 30-second answer

The Johor Bahru–Singapore RTS Link aims to carry passengers from February 2027, once trial runs finish by 31 December 2026 and independent safety certification and approvals from both countries follow. Johor plans a December dry run. Tenants should avoid paying an early RTS premium; buyers should compare walking routes that exist today.

Feb 2027target passenger service
~25 minentry-to-platform target
100automated immigration e-gates
10,000passengers per hour per direction

Key figures

  • By 31 December: final system tests and trial runs (joint statement).
  • Then: independent safety certification and approvals from both countries; passenger service targeted for February 2027.
  • December: Johor dry run to assess passenger movements and public transport (state exco Mohamad Fazli, via paultan.org).
  • Bukit Chagar station: a 25-minute target from station entry to platform, with 18 luggage scanners, 9 body scanners and 100 automated e-gates (The Edge).
  • Capacity: up to 10,000 passengers per hour per direction; about five minutes per trip; around 4 km long; about 40,000 daily riders expected at the start.
  • Singapore: more than 600 personnel took part in a multi-agency security exercise at Woodlands North on 11 to 12 November.

What happened

Infrastructure on both sides is substantially complete; what remains is testing, certification and approval. On 2 October the two governments set February 2027 as the target, subject to independent safety certification and regulatory approval.

Timeline: RTS Link milestones from the 2 October 2026 announcement to the February 2027 passenger service target
"Early 2027" for certification is our reading of the sequence; no date has been announced for it.

In Malaysia, after a change at the transport ministry, the Johor government said on 12 November that it is keeping the February target and will run a dry run in December. The Edge's special report describes the station design: co-located immigration for both countries on different levels, aiming for about 25 minutes from entry to boarding.

Developer connectivity visual for CTC SkyOne at Bukit Chagar showing links to the RTS station
Developer visual (CTC SkyOne). Check which walkways exist today before relying on quoted distances. Image: site media library.

Louis’s take: what it means for buyers

First, tenants should not rush into expensive long leases. Rents around Bukit Chagar may price in an RTS premium before and after opening. If you will commute to Singapore, consider a shorter first lease until real clearance times and fares are known.

Second, buyers should compare routes you can walk today. Many projects quote distances based on planned or unfinished link bridges. Our RTS page uses measured walking routes, so compare on that basis.

Twin Tower Residence serviced apartments at Bukit Chagar, Johor Bahru
Twin Tower Residence, completed in 2023 beside Bukit Chagar. Photo: site media library.

Third, count the whole commute, not just the five-minute ride: the walk to the station, the 25-minute entry-to-platform target, and the connection on the Singapore side.

Fourth, the date still depends on safety certification. February is a target, not a guarantee, so avoid basing a purchase on a specific opening month.

Names in English, Chinese and Malay

English中文Bahasa Malaysia
Johor Bahru–Singapore Rapid Transit System (RTS Link)新柔捷运系统(RTS Link)Sistem Transit Aliran Johor Bahru–Singapura (RTS Link)
RTS Operations Pte Ltd (RTSO)RTS 营运公司(RTSO)RTS Operations Pte Ltd
Ministry of Transport Malaysia马来西亚交通部Kementerian Pengangkutan Malaysia
Land Transport Authority (LTA), Singapore新加坡陆路交通管理局(LTA)Land Transport Authority (LTA), Singapura
Bukit Chagar station武吉查卡站Stesen Bukit Chagar
Woodlands North station兀兰北站Stesen Woodlands North

Frequently asked questions

When will the RTS Link open?

On 2 October 2026 the two governments said passenger service is targeted for February 2027, subject to independent safety certification and regulatory approvals from both countries.

How long is the trip from Bukit Chagar to Woodlands North?

About five minutes on the train. The Edge reports that Bukit Chagar station targets about 25 minutes from entry to platform, including screening and immigration for both countries.

Is the December dry run open to the public?

The Johor government has only said the December dry run will assess passenger movements and public transport arrangements; as of 24 November 2026 we have not seen an official announcement of public trial rides.

How much will the RTS fare be?

We could not find an officially announced fare at the time of writing. Singapore's transport ministry said on 4 November that usage will depend on factors including the fares set by the operator.